12861 W CORRENTI ST 91331

Certificate Information: 12861 W CORRENTI ST 91331

Application / Permit
22010-20000-02513
Plan Check / Job No.
B22VN07576
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New A.D.U 1,200 sq.ft. PER LAMC 12.22A.33(c) AND (d) ALL WORK DONE PER WFPP
Permit Issued
Issued on 12/13/2022
Issuing Office
Current Status
CofO Issued on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/7/2022 KHUONG TRUONG
Corrections Issued 6/7/2022 DANIEL SANJUAN
Applicant returned to address corrections 8/22/2022 KHUONG TRUONG
Applicant returned to address corrections 8/23/2022 KHUONG TRUONG
Plan Check Approved 11/30/2022 KHUONG TRUONG
Issued 12/13/2022 APPLICANT
CofO in Progress 5/16/2024 MICHEL ABAJAN
Permit Finaled 6/21/2024 RUBEN SALAS
CofO Issued 6/21/2024 RUBEN SALAS
Permit Finaled 6/21/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/9/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/27/2022 CARLOS AGUILERA
Sewer availability Cleared 6/28/2022 CARLOS AGUILERA
Clean Up Green Up Cleared 7/19/2022 DANG NGUYEN
Hydrant and Access approval Cleared 7/30/2022 KURT CORRAL
Low Impact Development Cleared 11/29/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/29/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/7/2023 Partial Inspection MICHEL ABAJAN
METHANE-Barrier 10/25/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 10/25/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 10/25/2023 Partial Approval MICHEL ABAJAN
Deputy Reinf. Concrete 10/27/2023 Approved MICHEL ABAJAN
Footing/Foundation/Slab 10/27/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/29/2023 Approved MICHEL ABAJAN
HVAC-Rough 11/29/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 11/29/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/4/2023 Approved MICHEL ABAJAN
Green Building Rough 12/4/2023 Approved MICHEL ABAJAN
METHANE-Rough 12/4/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 12/4/2023 Approved MICHEL ABAJAN
Insulation 12/8/2023 Approved MATTHEW NELSON
Drywall Nailing 12/14/2023 Approved MICHEL ABAJAN
Final 3/11/2024 Not Ready for Inspection MATTHEW NELSON
Green Building Final 3/11/2024 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 3/11/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 3/11/2024 Not Ready for Inspection MATTHEW NELSON
Underground Mechanical 4/18/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 4/25/2024 Approved MICHEL ABAJAN
Final 4/25/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 4/25/2024 Approved MICHEL ABAJAN
HVAC-Final 4/25/2024 Approved MICHEL ABAJAN
PLUMBING-Final 4/25/2024 Approved MICHEL ABAJAN
Service/Power Release 4/25/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 4/25/2024 Approved MICHEL ABAJAN
Final 5/16/2024 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 5/16/2024 Approved MICHEL ABAJAN