5306 E OAKLAND ST 1-2 90032
Certificate Information: 5306 E OAKLAND ST 1-2 90032
- Application / Permit
- 22010-20000-02510
- Plan Check / Job No.
- B22VN07554
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 41'6" X 32' THREE STORY DUPLEX, NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/30/2024
- Issuing Office
- Current Status
- CofO Issued on 10/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | RARES BODEA |
| Green Plans Picked Up | 6/17/2022 | APPLICANT |
| Corrections Issued | 6/21/2022 | RARES BODEA |
| Disabled Access Plans Picked Up | 6/21/2022 | APPLICANT |
| Quality Review Completed | 6/27/2022 | STEVEN KIM |
| Building Plans Picked Up | 6/28/2022 | APPLICANT |
| Applicant returned to address corrections | 11/14/2022 | RARES BODEA |
| Applicant returned to address corrections | 3/17/2023 | RARES BODEA |
| Plan Check Approved | 6/27/2023 | RARES BODEA |
| Issued | 7/30/2024 | APPLICANT |
| CofO in Progress | 10/2/2025 | LILIANA PORTILLO |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
| CofO Issued | 10/4/2025 | DEROLD HAUFF |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2022 | WALLIE JONG |
| Highway dedication | Cleared | 7/15/2022 | WALLIE JONG |
| Low Impact Development | Cleared | 12/6/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2022 | WALLIE JONG |
| Sewer availability | Cleared | 12/15/2022 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 12/22/2022 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 2/8/2023 | KURT CORRAL |
| GPI Written Notices | Cleared | 3/17/2023 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 3/17/2023 | RARES BODEA |
| SB8 RUD | Cleared | 6/6/2023 | JESSICA WANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Desai,, Anil T; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 9/13/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/13/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/25/2024 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 10/10/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 12/4/2024 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 1/14/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 1/14/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/4/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/10/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/10/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 2/10/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 2/10/2025 | Approved | LILIANA PORTILLO |
| Insulation | 2/26/2025 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 2/26/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 3/10/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 3/10/2025 | Approved | LILIANA PORTILLO |
| Insulation | 3/10/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/10/2025 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/19/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/13/2025 | Corrections Issued | LILIANA PORTILLO |
| Service/Power Release | 8/13/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/3/2025 | Approved | LILIANA PORTILLO |
| Gas Test | 9/3/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 9/3/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/8/2025 | Approved | LILIANA PORTILLO |
| Final | 9/8/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 9/8/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 9/8/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 9/8/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 9/8/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 9/12/2025 | Approved | LILIANA PORTILLO |
| Final | 9/29/2025 | Conditional Approval | LILIANA PORTILLO |
| Final | 10/1/2025 | OK to Issue CofO | LILIANA PORTILLO |