13947 W LOUVRE ST 91331

Certificate Information: 13947 W LOUVRE ST 91331

Application / Permit
22010-20000-02506
Plan Check / Job No.
B22VN07545
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW (40'X30') DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 12/5/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 LUISANGEL VALENZUELA
Corrections Issued 5/21/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 5/24/2022 APPLICANT
Plan Check Approved 12/5/2022 HAYATO TSUCHIYA
Issued 12/5/2022 APPLICANT
CofO in Progress 11/16/2023 MICHEL ABAJAN
Permit Finaled 2/14/2024 RUBEN SALAS
CofO Issued 2/14/2024 RUBEN SALAS
Permit Finaled 2/14/2024 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 9/21/2022 CHRIS VONG
Address approval Cleared 11/16/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 11/16/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/17/2022 MEGAN GODINEZ
Sewer availability Cleared 11/17/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/21/2023 Approved MICHEL ABAJAN
METHANE-Barrier 2/21/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 2/21/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/8/2023 Partial Approval MICHEL ABAJAN
Underground Mechanical 3/8/2023 Approved MICHEL ABAJAN
Gas Test 3/20/2023 Approved MICHEL ABAJAN
Underground Mechanical 3/20/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 4/6/2023 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 4/6/2023 Approved MICHEL ABAJAN
METHANE-Rough 4/6/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/6/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/28/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/28/2023 Approved MICHEL ABAJAN
Green Building Rough 4/28/2023 Approved MICHEL ABAJAN
HVAC-Rough 4/28/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 4/28/2023 Approved MICHEL ABAJAN
Insulation 5/18/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/18/2023 Approved MICHEL ABAJAN
Shower Pan 5/18/2023 Approved MICHEL ABAJAN
Drywall Nailing 6/15/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/15/2023 Approved MICHEL ABAJAN
Final 8/1/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 8/1/2023 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Final 8/1/2023 Approved MICHEL ABAJAN
Pre-Inspection 8/1/2023 Partial Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/1/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 8/1/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 8/1/2023 Corrections Issued MICHEL ABAJAN
Final 8/23/2023 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 8/23/2023 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 8/23/2023 Corrections Issued MICHEL ABAJAN
Smoke Detectors 8/23/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 11/6/2023 Approved MICHEL ABAJAN
Final 11/6/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 11/6/2023 Approved MICHEL ABAJAN
HVAC-Final 11/6/2023 Approved MICHEL ABAJAN
PLUMBING-Final 11/6/2023 Approved MICHEL ABAJAN
Service/Power Release 11/6/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 11/6/2023 Approved MICHEL ABAJAN
Final 11/16/2023 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 11/16/2023 Approved MICHEL ABAJAN