13947 W LOUVRE ST 91331
Certificate Information: 13947 W LOUVRE ST 91331
- Application / Permit
- 22010-20000-02506
- Plan Check / Job No.
- B22VN07545
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW (40'X30') DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/21/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| Plan Check Approved | 12/5/2022 | HAYATO TSUCHIYA |
| Issued | 12/5/2022 | APPLICANT |
| CofO in Progress | 11/16/2023 | MICHEL ABAJAN |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
| CofO Issued | 2/14/2024 | RUBEN SALAS |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/21/2022 | CHRIS VONG |
| Address approval | Cleared | 11/16/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 11/16/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/17/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/21/2023 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 2/21/2023 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 2/21/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/8/2023 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 3/8/2023 | Approved | MICHEL ABAJAN |
| Gas Test | 3/20/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/20/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 4/6/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 4/6/2023 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 4/6/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 4/6/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/28/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/28/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/28/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/28/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/28/2023 | Approved | MICHEL ABAJAN |
| Insulation | 5/18/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/18/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 5/18/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/15/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/15/2023 | Approved | MICHEL ABAJAN |
| Final | 8/1/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 8/1/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Final | 8/1/2023 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 8/1/2023 | Partial Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 8/1/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 8/1/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 8/23/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 8/23/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 8/23/2023 | Corrections Issued | MICHEL ABAJAN |
| Smoke Detectors | 8/23/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/6/2023 | Approved | MICHEL ABAJAN |
| Final | 11/6/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/6/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/6/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/6/2023 | Approved | MICHEL ABAJAN |
| Service/Power Release | 11/6/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 11/6/2023 | Approved | MICHEL ABAJAN |
| Final | 11/16/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 11/16/2023 | Approved | MICHEL ABAJAN |