13906 W FILMORE ST 91331

Certificate Information: 13906 W FILMORE ST 91331

Application / Permit
22010-20000-02500
Plan Check / Job No.
B22VN07537
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 35'-0" X 20'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 2/22/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2022 APPLICANT
Assigned to Plan Check Engineer 5/25/2022 ARTIN ZARUKIAN
Corrections Issued 5/28/2022 ARTIN ZARUKIAN
Building Plans Picked Up 6/3/2022 APPLICANT
Applicant returned to address corrections 11/23/2022 LUIS RINCON
Applicant returned to address corrections 2/15/2023 LUISANGEL VALENZUELA
Plan Check Approved 2/22/2023 OMAR GARNICA
Issued 2/22/2023 APPLICANT
CofO in Progress 12/30/2024 MICHEL ABAJAN
Permit Finaled 1/3/2025 RUBEN SALAS
CofO Issued 1/3/2025 RUBEN SALAS
Permit Finaled 1/3/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/16/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/29/2022 MEGAN GODINEZ
Sewer availability Cleared 8/29/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 10/7/2022 KURT CORRAL
Low Impact Development Cleared 11/22/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 2/21/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/5/2023 Conditional Approval MICHEL ABAJAN
METHANE-Barrier 5/5/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 5/5/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/31/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 5/31/2023 Not Ready for Inspection MICHEL ABAJAN
Insulation 5/31/2023 Partial Approval MICHEL ABAJAN
MERV13>=Rough 5/31/2023 Approved MICHEL ABAJAN
METHANE-Rough 5/31/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 5/31/2023 Not Ready for Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 5/31/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 8/30/2023 Approved MICHEL ABAJAN
HVAC-Rough 8/30/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 8/30/2023 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/25/2023 Approved MICHEL ABAJAN
Green Building Rough 9/25/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 9/25/2023 Approved MICHEL ABAJAN
Insulation 11/2/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/2/2023 Approved KEVIN BERBERYAN
Drywall Nailing 11/17/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/17/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 3/6/2024 Corrections Issued MICHEL ABAJAN
Final 4/8/2024 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 4/8/2024 Approved MICHEL ABAJAN
Green Building Final 4/8/2024 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Final 4/8/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 4/8/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 4/8/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/31/2024 Approved MICHEL ABAJAN
Final 5/31/2024 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 5/31/2024 Approved MICHEL ABAJAN
HVAC-Final 5/31/2024 Approved MICHEL ABAJAN
PLUMBING-Final 5/31/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 5/31/2024 Not Ready for Inspection MICHEL ABAJAN
Final 12/26/2024 OK to Issue CofO MICHEL ABAJAN