6853 N AMESTOY AVE 91406

Certificate Information: 6853 N AMESTOY AVE 91406

Application / Permit
22010-20000-02495
Plan Check / Job No.
B22VN07528
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/18/2022
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 DANIEL YIP
Corrections Issued 5/20/2022 DANIEL YIP
Plan Check Approved 11/7/2022 DANIEL YIP
Plan Check Approved 11/16/2022 DANIEL YIP
Issued 11/18/2022 APPLICANT
CofO in Progress 10/22/2024 JON MCHUGH
No Progress 1/9/2025 SEAN WIRCH
CofO in Progress 1/9/2025 SEAN WIRCH
CofO in Progress 9/24/2025 JON MCHUGH
Permit Finaled 9/25/2025 JOHN JANSON
CofO Issued 9/25/2025 JOHN JANSON
Permit Finaled 9/25/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/23/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/23/2022 CARLOS AGUILERA
Sewer availability Cleared 8/23/2022 CARLOS AGUILERA
Construction near power lines Cleared 10/27/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 12/6/2022 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 12/8/2022 Corrections Issued JON MCHUGH
PLUMBING-Rough 12/8/2022 Corrections Issued JON MCHUGH
Wood Frame 12/8/2022 Corrections Issued JON MCHUGH
Insulation 12/19/2022 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 1/3/2023 No Access for Inspection JON MCHUGH
Interior/Exterior Lathing 1/10/2023 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 1/17/2023 Partial Approval SEAN HAUPT
Pre-Inspection 1/17/2023 Partial Inspection JUSTIN HAWLEY
Drywall Nailing 2/1/2023 Approved JUSTIN HAWLEY
Insulation 2/1/2023 Approved JUSTIN HAWLEY
Gas Test 5/5/2023 Not Ready for Inspection JON MCHUGH
Rough-Elec/Plmb/HVAC 5/5/2023 Corrections Issued JON MCHUGH
Pre-Inspection 7/25/2023 Approved JEFFREY BULL
PLUMBING-Rough 8/17/2023 Corrections Issued JON MCHUGH
Gas Test 9/8/2023 Approved JUSTIN HAWLEY
Underground Mechanical 9/8/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Final 6/26/2024 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 6/26/2024 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 7/23/2024 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 9/26/2024 Approved JON MCHUGH
Final 9/26/2024 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Approved JON MCHUGH
Smoke Detectors 9/26/2024 Approved JON MCHUGH
ELECTRICAL-Final 10/21/2024 Approved JON MCHUGH
Final 10/21/2024 OK to Issue CofO JON MCHUGH
HVAC-Final 10/21/2024 Approved JON MCHUGH
PLUMBING-Final 10/21/2024 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved JON MCHUGH
Final 9/24/2025 OK to Issue CofO JON MCHUGH