12151 W BLIX ST 91607
Certificate Information: 12151 W BLIX ST 91607
- Application / Permit
- 22010-20000-02487
- Plan Check / Job No.
- B22VN07516
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan new sfd
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- Issued on 3/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 6/28/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/1/2022 | FARUK SEZER |
| Building Plans Picked Up | 11/1/2022 | APPLICANT |
| Plan Check Approved | 8/29/2023 | ARSALAN SHABESTARI |
| No Progress | 1/29/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/29/2024 | ARSALAN SHABESTARI |
| Issued | 3/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Permit | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/31/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/31/2023 | RIDWAN HARDY |
| Specific Plan | Cleared | 4/7/2023 | CHRISTIAN PEARSON |
| Hydrant and Access approval | Cleared | 4/15/2023 | KURT CORRAL |
| ZI | Cleared | 4/18/2023 | CHRISTIAN PEARSON |
| Low Impact Development | Cleared | 5/18/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 5/20/2023 | CARLOS AGUILERA |
| Tract Map conditions | Cleared | 5/24/2023 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/4/2026 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 3/16/2026 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/17/2026 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Partial Approval | CHRISTOPHE COCHRAN |