18564 W ARMINTA ST 91335
Certificate Information: 18564 W ARMINTA ST 91335
- Application / Permit
- 22010-20000-02471
- Plan Check / Job No.
- B22VN07461
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1,102 SQ. FT. DETACHED ACCESSORY DWELLING UNIT PER ENGINEER DESIGN.
- Permit Issued
- Issued on 7/20/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2022 | JEFFREY TANGONAN |
| Corrections Issued | 5/17/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 5/20/2022 | APPLICANT |
| Plan Check Approved | 7/18/2022 | DANIEL SANJUAN |
| Issued | 7/20/2022 | APPLICANT |
| CofO in Progress | 3/4/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 3/10/2025 | JOHN JANSON |
| CofO Issued | 3/10/2025 | JOHN JANSON |
| Permit Finaled | 3/10/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 7/12/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/14/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 7/14/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 7/14/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 7/14/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/7/2024 | Partial Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 6/17/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 6/17/2024 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 6/24/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 7/24/2024 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | KRISTEN CAUSEY |
| PLUMBING-Rough | 7/24/2024 | Approved | KRISTEN CAUSEY |
| Shower Pan | 11/8/2024 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 11/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 11/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 11/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 11/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 11/14/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Green Building Rough | 11/14/2024 | Approved | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 11/14/2024 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 11/14/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 11/18/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 11/20/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 11/20/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 1/28/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 1/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 1/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/13/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Final | 2/13/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 2/13/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 2/13/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 2/13/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/19/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 2/19/2025 | Corrections Issued | JUAN ALVARADO |
| HVAC-Final | 2/19/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 2/19/2025 | Approved | JUAN ALVARADO |
| Service/Power Release | 2/19/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 2/25/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 3/3/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/3/2025 | OK to Issue CofO | ARUTYUN MADATYAN |