16842 W ADDISON ST 91436

Certificate Information: 16842 W ADDISON ST 91436

Application / Permit
22010-20000-02470
Plan Check / Job No.
B22VN07460
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR SHAPED 82'-1" x 46' TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
Permit Issued
Issued on 8/19/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 SEAN SHAHMIRI
Corrections Issued 5/31/2022 SEAN SHAHMIRI
Quality Review Completed 6/2/2022 OMID HEDAYAT
Building Plans Picked Up 6/6/2022 APPLICANT
Applicant returned to address corrections 7/29/2022 SEAN SHAHMIRI
Plan Check Approved 8/11/2022 SEAN SHAHMIRI
Issued 8/19/2022 APPLICANT
CofO in Progress 6/16/2023 VINCENT HANLEY
Permit Finaled 8/23/2023 JOHN JANSON
CofO Issued 8/23/2023 JOHN JANSON
Permit Finaled 8/23/2023 JOHN JANSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/30/2022 KURT CORRAL
Address approval Cleared 8/4/2022 LEE GUILBEAUX
Low Impact Development Cleared 8/4/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 8/4/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/8/2022 LEE GUILBEAUX
Sewer availability Cleared 8/8/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/9/2022 Approved VINCENT HANLEY
PLUMBING-Rough 9/9/2022 Partial Approval VINCENT HANLEY
Sewer 9/9/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/20/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval VINCENT HANLEY
Green Building Rough 9/20/2022 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 9/20/2022 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/7/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 11/2/2022 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 11/9/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 11/9/2022 Approved VINCENT HANLEY
Green Building Rough 11/9/2022 Approved VINCENT HANLEY
PLUMBING-Rough 11/9/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/9/2022 Approved VINCENT HANLEY
Insulation 11/16/2022 Not Ready for Inspection VINCENT HANLEY
Shower Pan 11/16/2022 Approved VINCENT HANLEY
Insulation 11/18/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 11/18/2022 Partial Approval JESUS PINEDA
Drywall Nailing 11/22/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/22/2022 Approved VINCENT HANLEY
Final 5/9/2023 Corrections Issued VINCENT HANLEY
Green Building Final 5/9/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 5/9/2023 Approved VINCENT HANLEY
Smoke Detectors 5/9/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 6/13/2023 Approved VINCENT HANLEY
Final 6/13/2023 Corrections Issued VINCENT HANLEY
HVAC-Final 6/13/2023 Approved VINCENT HANLEY
PLUMBING-Final 6/13/2023 Approved VINCENT HANLEY
Final 6/16/2023 OK to Issue CofO VINCENT HANLEY