10815 W ART ST 91040
Certificate Information: 10815 W ART ST 91040
- Application / Permit
- 22010-20000-02453
- Plan Check / Job No.
- B22VN07402
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 24' x 33' DETACHED OPEN TRELLIS - WORK PER ENGINEER.
- Permit Issued
- Issued on 3/24/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2022 | SEAN SHAHMIRI |
| Corrections Issued | 5/17/2022 | SEAN SHAHMIRI |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| Applicant returned to address corrections | 11/8/2022 | ROSENDO MEDINA |
| Plan Check Approved | 1/13/2023 | DANIEL ABRAMYAN |
| Issued | 3/24/2023 | APPLICANT |
| CofO in Progress | 5/19/2023 | DAVID ANDERSON |
| CofO Issued | 5/26/2023 | MICHAEL SMITH |
| Permit Finaled | 5/26/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 11/8/2022 | ROSENDO MEDINA |
| Grading Pre-Inspection | Cleared | 11/8/2022 | ROSENDO MEDINA |
| Miscellaneous | Cleared | 11/8/2022 | SPENCER WEJROWSKI |
| Low Impact Development | Cleared | 11/9/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/9/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2022 | CARLOS AGUILERA |
| Specific Plan | Cleared | 12/7/2022 | CECILIA CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Pre-Inspection | 4/3/2023 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/7/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/9/2023 | Approved | DAVID ANDERSON |
| Final | 5/9/2023 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 5/9/2023 | Approved | DAVID ANDERSON |
| Smoke Detectors | 5/9/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 5/9/2023 | Approved | DAVID ANDERSON |
| Final | 5/19/2023 | OK to Issue CofO | DAVID ANDERSON |