10047 N KEOKUK AVE 91311
Certificate Information: 10047 N KEOKUK AVE 91311
- Application / Permit
- 22010-20000-02447
- Plan Check / Job No.
- B22VN07387
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (29'-6"x 24'-6") 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER EMGINEER.
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Current Status
- CofO Issued on 8/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | SEAN SHAHMIRI |
| Corrections Issued | 6/22/2022 | TROY DEGUZMAN |
| Quality Review Completed | 7/7/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/29/2022 | TROY DEGUZMAN |
| Applicant returned to address corrections | 8/31/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/12/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 11/14/2022 | SEAN SHAHMIRI |
| Issued | 12/22/2022 | APPLICANT |
| CofO in Progress | 6/30/2025 | DAVID SCANTLIN |
| Permit Finaled | 8/18/2025 | JOHN JANSON |
| Permit Finaled | 8/18/2025 | JOHN JANSON |
| CofO Issued | 8/18/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 6/30/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 7/30/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 8/29/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/30/2022 | JOSE DUARTE-DIAZ |
| Green Code | Cleared | 9/3/2022 | TROY DEGUZMAN |
| Construction within easement | Cleared | 10/25/2022 | RIDWAN HARDY |
Contact Information
| Architect | Akraa,, Ghazwan; Lic. No.: C31639 | 14617 VICTORY BLVD #3 VAN NUYS, CA 91411 |
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: C93049 | 7812 VASSAR AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2023 | Corrections Issued | JOHN KIDWELL |
| PLUMBING-Rough | 9/6/2023 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 9/6/2023 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/13/2023 | Approved | JOHN KIDWELL |
| Pre-Inspection | 9/13/2023 | Partial Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/10/2023 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 10/10/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 10/10/2023 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/20/2023 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 10/20/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 10/20/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | JOHN KIDWELL |
| HVAC-Final | 11/6/2023 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 11/6/2023 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 11/6/2023 | Approved | JOHN KIDWELL |
| Sewer | 11/6/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 11/21/2023 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 11/21/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 11/21/2023 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 11/21/2023 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 11/21/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/20/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/20/2023 | Approved | DAVID SCANTLIN |
| Insulation | 12/20/2023 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 12/20/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 12/29/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/29/2023 | Partial Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/29/2023 | Partial Approval | JOHN KIDWELL |
| Gas Test | 2/21/2024 | Approved | KRISTEN CAUSEY |
| Service/Power Release | 2/21/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Final | 5/3/2024 | Approved | DAVID SCANTLIN |
| Final | 5/3/2024 | Corrections Issued | DAVID SCANTLIN |
| HVAC-Final | 5/3/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Final | 5/3/2024 | Approved | DAVID SCANTLIN |
| Final | 2/4/2025 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 2/4/2025 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 2/4/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 2/4/2025 | Approved | DAVID SCANTLIN |
| Final | 6/27/2025 | OK to Issue CofO | DAVID SCANTLIN |
| Service/Power Release | 6/27/2025 | Approved | DAVID SCANTLIN |