10047 N KEOKUK AVE 91311

Certificate Information: 10047 N KEOKUK AVE 91311

Application / Permit
22010-20000-02447
Plan Check / Job No.
B22VN07387
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (29'-6"x 24'-6") 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER EMGINEER.
Permit Issued
Issued on 12/22/2022
Issuing Office
Current Status
CofO Issued on 8/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 SEAN SHAHMIRI
Corrections Issued 6/22/2022 TROY DEGUZMAN
Quality Review Completed 7/7/2022 OMID HEDAYAT
Applicant returned to address corrections 7/29/2022 TROY DEGUZMAN
Applicant returned to address corrections 8/31/2022 SEAN SHAHMIRI
Applicant returned to address corrections 9/12/2022 SEAN SHAHMIRI
Plan Check Approved 11/14/2022 SEAN SHAHMIRI
Issued 12/22/2022 APPLICANT
CofO in Progress 6/30/2025 DAVID SCANTLIN
Permit Finaled 8/18/2025 JOHN JANSON
Permit Finaled 8/18/2025 JOHN JANSON
CofO Issued 8/18/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/28/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/30/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/30/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 7/30/2022 KURT CORRAL
Low Impact Development Cleared 8/29/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/30/2022 JOSE DUARTE-DIAZ
Green Code Cleared 9/3/2022 TROY DEGUZMAN
Construction within easement Cleared 10/25/2022 RIDWAN HARDY

Contact Information

Architect Akraa,, Ghazwan; Lic. No.: C31639 14617 VICTORY BLVD #3      VAN NUYS, CA 91411
Contractor Owner-Builder       ,
Engineer Mniarji,, Majd Sameer; Lic. No.: C93049 7812 VASSAR AVENUE      CANOGA PARK, CA 91304

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/6/2023 Corrections Issued JOHN KIDWELL
PLUMBING-Rough 9/6/2023 Partial Approval JOHN KIDWELL
Pre-Inspection 9/6/2023 Partial Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 9/13/2023 Approved JOHN KIDWELL
Footing/Foundation/Slab 9/13/2023 Approved JOHN KIDWELL
Pre-Inspection 9/13/2023 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 10/10/2023 Partial Approval JOHN KIDWELL
Green Building Rough 10/10/2023 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 10/10/2023 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 10/20/2023 Partial Approval JOHN KIDWELL
Green Building Rough 10/20/2023 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 10/20/2023 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval JOHN KIDWELL
HVAC-Final 11/6/2023 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 11/6/2023 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 11/6/2023 Approved JOHN KIDWELL
Sewer 11/6/2023 Approved JOHN KIDWELL
ELECTRICAL-Rough 11/21/2023 Approved DAVID SCANTLIN
HVAC-Rough 11/21/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 11/21/2023 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 11/21/2023 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 11/21/2023 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/20/2023 Approved DAVID SCANTLIN
Green Building Rough 12/20/2023 Approved DAVID SCANTLIN
Insulation 12/20/2023 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 12/20/2023 Approved DAVID SCANTLIN
Drywall Nailing 12/29/2023 Approved JOHN KIDWELL
ELECTRICAL-Rough 12/29/2023 Partial Inspection JOHN KIDWELL
Interior/Exterior Lathing 12/29/2023 Partial Approval JOHN KIDWELL
Gas Test 2/21/2024 Approved KRISTEN CAUSEY
Service/Power Release 2/21/2024 Not Ready for Inspection KRISTEN CAUSEY
ELECTRICAL-Final 5/3/2024 Approved DAVID SCANTLIN
Final 5/3/2024 Corrections Issued DAVID SCANTLIN
HVAC-Final 5/3/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Final 5/3/2024 Approved DAVID SCANTLIN
Final 2/4/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 2/4/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Approved DAVID SCANTLIN
Service/Power Release 2/4/2025 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 2/4/2025 Approved DAVID SCANTLIN
Final 6/27/2025 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 6/27/2025 Approved DAVID SCANTLIN