3533 S ROSEWOOD AVE 90066

Certificate Information: 3533 S ROSEWOOD AVE 90066

Application / Permit
22010-20000-02438
Plan Check / Job No.
B22VN07316
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED REC. ROOM BLDG, (31'-0"X10'-0"), 190 SQFT WITH BATH ACCESSED FROM THE OUTSIDE. TO BE ISSUED WITH POOL
Permit Issued
Issued on 10/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 PETER MOSESIAN
Corrections Issued 5/22/2022 PETER MOSESIAN
Quality Review Completed 5/27/2022 OMID HEDAYAT
Building Plans Picked Up 6/1/2022 APPLICANT
Plan Check Approved 10/14/2022 PETER MOSESIAN
Issued 10/27/2022 APPLICANT
CofO in Progress 7/7/2023 MICHAEL PELHAM
Permit Finaled 7/8/2023 DANIEL ORRANTE
CofO Issued 7/8/2023 DANIEL ORRANTE
Permit Finaled 7/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 8/31/2022 JULIAN SUNG
Hydrant and Access approval Cleared 9/9/2022 ROBERT DUFF
Construction near power lines Cleared 10/4/2022 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 10/17/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/20/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/1/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/22/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 12/22/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 2/15/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 2/15/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 2/15/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 2/22/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 2/22/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 3/6/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 3/6/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/6/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 3/6/2023 Approved JESUS RODRIGUEZ
Insulation 3/9/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 3/10/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/6/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/6/2023 Approved JESUS RODRIGUEZ
Final 6/6/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 6/6/2023 Approved JESUS RODRIGUEZ
HVAC-Final 6/6/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/6/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/6/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 6/6/2023 Conditional Approval JESUS RODRIGUEZ
Smoke Detectors 6/6/2023 Approved JESUS RODRIGUEZ
Final 7/6/2023 Partial Approval JESUS RODRIGUEZ
Service/Power Release 7/6/2023 Approved JESUS RODRIGUEZ
Final 7/7/2023 Partial Approval JESUS RODRIGUEZ