3533 S ROSEWOOD AVE 90066
Certificate Information: 3533 S ROSEWOOD AVE 90066
- Application / Permit
- 22010-20000-02438
- Plan Check / Job No.
- B22VN07316
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW DETACHED REC. ROOM BLDG, (31'-0"X10'-0"), 190 SQFT WITH BATH ACCESSED FROM THE OUTSIDE. TO BE ISSUED WITH POOL
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | PETER MOSESIAN |
| Corrections Issued | 5/22/2022 | PETER MOSESIAN |
| Quality Review Completed | 5/27/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| Plan Check Approved | 10/14/2022 | PETER MOSESIAN |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 7/7/2023 | MICHAEL PELHAM |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
| CofO Issued | 7/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/31/2022 | JULIAN SUNG |
| Hydrant and Access approval | Cleared | 9/9/2022 | ROBERT DUFF |
| Construction near power lines | Cleared | 10/4/2022 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 10/17/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/1/2022 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/22/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/15/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 2/15/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/15/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/22/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/22/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 3/6/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/6/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 3/6/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/9/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/10/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| Final | 6/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 6/6/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Smoke Detectors | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| Final | 7/6/2023 | Partial Approval | JESUS RODRIGUEZ |
| Service/Power Release | 7/6/2023 | Approved | JESUS RODRIGUEZ |
| Final | 7/7/2023 | Partial Approval | JESUS RODRIGUEZ |