3533 S ROSEWOOD AVE 90066

Certificate Information: 3533 S ROSEWOOD AVE 90066

Application / Permit
22010-20000-02437
Plan Check / Job No.
B22VN07316
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD (2588 SQFT) W/ATT. 2 CAR GARAGE (321 SQFT), (30'-8"x69'-2") AND ROOFTOP DECK ABOVE W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 PETER MOSESIAN
Corrections Issued 5/22/2022 PETER MOSESIAN
Quality Review Completed 5/27/2022 OMID HEDAYAT
Building Plans Picked Up 6/1/2022 APPLICANT
Plan Check Approved 10/14/2022 PETER MOSESIAN
Issued 10/27/2022 APPLICANT
CofO in Progress 7/7/2023 JESUS RODRIGUEZ
Permit Finaled 7/8/2023 DANIEL ORRANTE
CofO Issued 7/8/2023 DANIEL ORRANTE
Permit Finaled 7/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 6/25/2022 STEVEN JIN
Hydrant and Access approval Cleared 7/5/2022 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 8/26/2022 STEVEN JIN
Low Impact Development Cleared 8/31/2022 JULIAN SUNG
Sewer availability Cleared 9/7/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 9/9/2022 DINAH GARIN
Trees in Parkway Cleared 9/9/2022 ADALBERTO VERA
Specific Plan Cleared 9/20/2022 EDUARDO HERMOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/1/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/22/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 12/22/2022 Approved JESUS RODRIGUEZ
Deputy Reinf. Concrete 12/27/2022 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval JESUS RODRIGUEZ
Gas Test 1/24/2023 Not Ready for Inspection JESUS RODRIGUEZ
Sewer 1/24/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Conditional Approval JESUS RODRIGUEZ
Deputy Steel/Welding 1/30/2023 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 2/15/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 2/15/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 2/15/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 2/22/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 3/6/2023 Approved JESUS RODRIGUEZ
Final 3/6/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 3/6/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/6/2023 Approved JESUS RODRIGUEZ
Shower Pan 3/6/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 3/6/2023 Approved JESUS RODRIGUEZ
Insulation 3/9/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/9/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 3/10/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/6/2023 Approved JESUS RODRIGUEZ
Final 6/6/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 6/6/2023 Approved JESUS RODRIGUEZ
HVAC-Final 6/6/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/6/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/6/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 6/6/2023 Conditional Approval JESUS RODRIGUEZ
Smoke Detectors 6/6/2023 Approved JESUS RODRIGUEZ
Final 7/6/2023 OK to Issue CofO JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 7/6/2023 Approved JESUS RODRIGUEZ