17655 W BELINDA ST 91316
Certificate Information: 17655 W BELINDA ST 91316
- Application / Permit
- 22010-20000-02436
- Plan Check / Job No.
- B22VN07307
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED GARAGE ; FIRE SPRINKLER NFPA 13D
- Permit Issued
- Issued on 10/11/2024
- Issuing Office
- Valley
- Current Status
- Issued on 10/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/13/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 6/17/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/21/2022 | APPLICANT |
| Plan Check Approved | 10/9/2024 | MOHAMMAD ESMAILI |
| Issued | 10/11/2024 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/11/2023 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 10/11/2023 | MOHAMMAD ESMAILI |
| BHO/Hillside ordinance | Cleared | 11/30/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 11/30/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 11/30/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 11/30/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/19/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 4/30/2024 | VICTOR MENDOZA |
| Hydrant and Access approval | Cleared | 8/22/2024 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 8/28/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 7/8/2025 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 7/8/2025 | Not Ready for Inspection | JON MCHUGH |
| Deputy Reinf. Concrete | 7/23/2025 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 7/23/2025 | Not Ready for Inspection | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 7/24/2025 | Partial Approval | SEAN WIRCH |
| Deputy Reinf. Concrete | 11/24/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 11/24/2025 | Not Ready for Inspection | ROBERT GOLD |
| Footing/Foundation/Slab | 11/25/2025 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 12/4/2025 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 1/23/2026 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2026 | Partial Approval | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 7/15/2026 | Approved | JOHN KIDWELL |