17655 W BELINDA ST 91316

Certificate Information: 17655 W BELINDA ST 91316

Application / Permit
22010-20000-02435
Plan Check / Job No.
B22VN07307
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/ATT. GARAGE, FIRE SPRINKLER NFPA 13D
Permit Issued
Issued on 10/11/2024
Issuing Office
Valley
Current Status
Issued on 10/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 MOHAMMAD ESMAILI
Corrections Issued 6/13/2022 MOHAMMAD ESMAILI
Quality Review Completed 6/17/2022 OMID HEDAYAT
Building Plans Picked Up 6/21/2022 APPLICANT
Plan Check Approved 10/9/2024 MOHAMMAD ESMAILI
Issued 10/11/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/25/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 6/25/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 6/25/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 6/25/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 6/25/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/27/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 11/27/2023 LEE GUILBEAUX
Distance to fire station Cleared 3/20/2024 KURT CORRAL
Hydrant and Access approval Cleared 3/20/2024 KURT CORRAL
GPI Written Notices Cleared 4/22/2024 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 4/22/2024 MOHAMMAD ESMAILI
Miscellaneous Cleared 4/22/2024 MOHAMMAD ESMAILI
Private sewage disp. approval Cleared 4/23/2024 MOHAMMAD ESMAILI
Low Impact Development Cleared 4/30/2024 VICTOR MENDOZA
Excavation more than 5-ft deep Cleared 5/1/2024 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 5/1/2024 JOHN LIN
Sewer availability Cleared 8/22/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/3/2024 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 12/11/2024 Corrections Issued THOMAS FINNILA
Underground Mechanical 12/11/2024 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 12/16/2024 Partial Approval SEAN WIRCH
PLUMBING-Rough 12/16/2024 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 12/17/2024 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 12/23/2024 Approved THOMAS FINNILA
Deputy Reinf. Concrete 12/24/2024 Partial Approval SEAN WIRCH
Deputy Wood Construction 2/11/2025 Conditional Approval THOMAS FINNILA
Piling/Pier/Caisson 3/7/2025 Partial Approval JOHN HAYES
Deputy Reinf. Concrete 3/10/2025 Conditional Approval THOMAS FINNILA
Piling/Pier/Caisson 3/10/2025 Not Ready for Inspection THOMAS FINNILA
Deputy Reinf. Concrete 3/12/2025 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 3/17/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 4/3/2025 Conditional Approval ROBERT GOLD
Deputy Other (see comments) 4/7/2025 Conditional Approval ROBERT GOLD
Piling/Pier/Caisson 4/7/2025 Partial Inspection JOHN KIDWELL
Deputy Other (see comments) 4/8/2025 Partial Approval SEAN WIRCH
Deputy Other (see comments) 4/9/2025 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 4/9/2025 Partial Approval SEAN WIRCH
Piling/Pier/Caisson 4/11/2025 Partial Approval THOMAS FINNILA
Deputy Other (see comments) 4/14/2025 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 4/14/2025 Partial Approval SEAN WIRCH
Deputy Wood Construction 4/15/2025 Conditional Approval HENRY KIM
Deputy Reinf. Concrete 4/17/2025 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Not Ready for Inspection THOMAS FINNILA
Deputy Reinf. Concrete 4/28/2025 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 4/28/2025 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 4/29/2025 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 5/6/2025 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 5/13/2025 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 5/13/2025 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 5/16/2025 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 5/20/2025 Conditional Approval JOHN COLEMAN
Deputy Reinf. Concrete 6/20/2025 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/20/2025 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 6/23/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 7/8/2025 Partial Approval JON MCHUGH
Deputy Reinf. Concrete 7/11/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 7/24/2025 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 7/25/2025 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 7/28/2025 Partial Approval SEAN WIRCH
Excavation/Setback/Form/Re-Bar 8/11/2025 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 8/12/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 8/22/2025 Not Ready for Inspection JOHN KIDWELL
Deputy Reinf. Concrete 8/25/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 8/25/2025 Not Ready for Inspection JOHN KIDWELL
Deputy Reinf. Concrete 8/29/2025 Conditional Approval MORRIS JACKSON
Deputy Wood Construction 9/17/2025 Partial Approval SEAN WIRCH
Deputy Wood Construction 9/22/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 10/8/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/8/2025 Conditional Approval JOHN KIDWELL
Deputy Reinf. Concrete 10/15/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/15/2025 Corrections Issued JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/21/2025 Not Ready for Inspection JOHN KIDWELL
Deputy Reinf. Concrete 10/22/2025 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 10/31/2025 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 10/31/2025 Approved JOHN KIDWELL
Green Building Rough 10/31/2025 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 10/31/2025 Approved JOHN KIDWELL
PLUMBING-Rough 10/31/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 10/31/2025 Not Ready for Inspection JOHN KIDWELL
Deputy Reinf. Concrete 11/3/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 11/3/2025 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 11/4/2025 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 12/3/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 12/3/2025 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 12/4/2025 Partial Approval JOHN KIDWELL
SWPPP-Const. Storm Water 12/24/2025 Violation Observed JOHN KIDWELL
BUILDING-Rough-Frame 1/13/2026 Approved JOHN KIDWELL
Green Building Rough 1/13/2026 Approved JOHN KIDWELL
Insulation 1/13/2026 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/13/2026 Partial Approval JOHN KIDWELL
Shower Pan 1/13/2026 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 1/13/2026 Approved JOHN KIDWELL
Drywall Nailing 1/29/2026 Approved JOHN KIDWELL
Special/Order Compliance 2/19/2026 Partial Inspection SEAN WIRCH
Interior/Exterior Lathing 3/16/2026 Partial Approval JOHN KIDWELL