12915 W ADDISON ST 91423
Certificate Information: 12915 W ADDISON ST 91423
- Application / Permit
- 22010-20000-02433
- Plan Check / Job No.
- B22VN07304
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD (3520 SQFT) W/ATT. 2-CAR GARAGE (390 SQFT), AND ATTACHED OPEN TRELLIS, (55'-0"x54'-6"), REAR BUILDING W/ NFPA -13R SPRINKLERS THROUGHOUT PER SB9
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | PETER MOSESIAN |
| Corrections Issued | 6/10/2022 | PETER MOSESIAN |
| Quality Review Completed | 6/21/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Plan Check Approved | 2/10/2023 | PETER MOSESIAN |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 12/19/2023 | JOSE AVILA |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 11/17/2022 | ANTHONY VARGAS |
| Sewer availability | Cleared | 11/17/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/15/2022 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 1/12/2023 | KENTON TRINH |
| Hydrant and Access approval | Cleared | 1/30/2023 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/14/2023 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 6/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 6/28/2023 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/28/2023 | Approved | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 6/29/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 7/31/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 7/31/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 8/3/2023 | Approved | KIRK SANDERS |
| Shower Pan | 8/3/2023 | Approved | KIRK SANDERS |
| Deputy Wood Construction | 8/9/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 8/9/2023 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 8/9/2023 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 8/18/2023 | Partial Approval | KIRK SANDERS |
| Sewer | 8/18/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 8/18/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 8/22/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/24/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 8/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 8/29/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 8/29/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 8/29/2023 | Approved | KIRK SANDERS |
| Insulation | 9/1/2023 | Approved | KIRK SANDERS |
| Sewer | 9/1/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 9/8/2023 | Approved | KIRK SANDERS |
| Gas Test | 11/20/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 12/12/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 12/12/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 12/12/2023 | Approved | JOSE AVILA |
| Final | 12/15/2023 | Corrections Issued | JOSE AVILA |
| Final | 12/18/2023 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 12/18/2023 | Approved | JOSE AVILA |