5628-5630 N BECK AVE 91601
Certificate Information: 5628-5630 N BECK AVE 91601
- Application / Permit
- 22010-20000-02430
- Plan Check / Job No.
- B22VN07301
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: PROPOSED DETACHED 2 UNITS, ONE UNIT SHALL BE AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A), SECOND UNIT SHALL BE ONE UNIT PER SB9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21. ***BLDG SHALL BE SPRINKLERED PER NFPA 13 D***
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- CofO Issued on 7/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | MICHAEL LOPEZ |
| Corrections Issued | 6/24/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 7/1/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/6/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 2/2/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 3/16/2023 | MICHAEL LOPEZ |
| Issued | 3/17/2023 | SHANNON HAAS |
| CofO in Progress | 5/30/2024 | KEVIN BERBERYAN |
| CofO Issued | 7/2/2024 | RUBEN SALAS |
| Permit Finaled | 7/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/18/2022 | RIDWAN HARDY |
| Address approval | Cleared | 8/22/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/29/2022 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 12/29/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/29/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/12/2023 | CARLOS AGUILERA |
Contact Information
| Architect | Baek,, Sunpil; Lic. No.: NA35323 | , |
| Contractor | Sunway Construction Inc; Lic. No.: 697180-B | , |
| Engineer | Hwang,, Junho; Lic. No.: NA5592 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/7/2023 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 6/7/2023 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/27/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 7/21/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/31/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 8/31/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/31/2023 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 9/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 9/7/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 9/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/18/2023 | Approved | DAVID MATSON |
| Green Building Rough | 9/18/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 9/18/2023 | Partial Approval | DAVID MATSON |
| Verify Sprinkler Sign Off | 9/18/2023 | Approved | DAVID MATSON |
| Insulation | 10/4/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/12/2023 | Approved | RYAN SALAZAR |
| Sewer | 11/20/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 11/27/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 12/13/2023 | Partial Approval | JOHN COLEMAN |
| HVAC-Final | 3/4/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 3/12/2024 | Approved | JOHN COLEMAN |
| Gas Test | 3/12/2024 | Approved | JOHN COLEMAN |
| HVAC-Final | 3/12/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 4/23/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 5/20/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/20/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/20/2024 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 5/20/2024 | Corrections Issued | MISAEL ESPARZA |
| Smoke Detectors | 5/20/2024 | Approved | MISAEL ESPARZA |
| Final | 5/29/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 5/29/2024 | Approved | KEVIN BERBERYAN |