2247 1/4 S COCHRAN AVE 90016
Certificate Information: 2247 1/4 S COCHRAN AVE 90016
- Application / Permit
- 22010-20000-02376
- Plan Check / Job No.
- B22VN07144
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21' x 31' (651 SQ. FT.) DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g). ALL WORK PER WFPP
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- Current Status
- CofO Issued on 8/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2022 | JEFFREY TANGONAN |
| Corrections Issued | 5/14/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 5/17/2022 | APPLICANT |
| Applicant returned to address corrections | 8/26/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 8/29/2022 | OMAR GARNICA |
| Issued | 9/9/2022 | APPLICANT |
| CofO in Progress | 8/8/2023 | JOSE AVILA |
| Permit Finaled | 8/10/2023 | DEROLD HAUFF |
| CofO Issued | 8/10/2023 | DEROLD HAUFF |
| Permit Finaled | 8/10/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2022 | JEANIE LAM |
| Sewer availability | Cleared | 5/25/2022 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 6/9/2022 | MICHAEL SOTO |
| Construction near power lines | Cleared | 7/6/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 8/12/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 8/15/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/3/2022 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 12/6/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 1/27/2023 | Corrections Issued | JOSE AVILA |
| Gas Test | 1/27/2023 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 1/27/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 1/31/2023 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 1/31/2023 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 1/31/2023 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/2/2023 | Partial Approval | JOSE AVILA |
| Green Building Rough | 2/2/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 2/2/2023 | Approved | JOSE AVILA |
| Insulation | 2/13/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/13/2023 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 2/13/2023 | Partial Approval | JOSE AVILA |
| Drywall Nailing | 2/21/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/21/2023 | Approved | JOSE AVILA |
| Service/Power Release | 3/30/2023 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 6/15/2023 | Approved | JOSE AVILA |
| Final | 6/15/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 6/15/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/15/2023 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 6/15/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 6/15/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 6/15/2023 | Approved | JOSE AVILA |
| Special/Order Compliance | 6/22/2023 | Corrections Issued | JOSE AVILA |
| Final | 7/3/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | JOSE AVILA |
| ELECTRICAL-Final | 8/2/2023 | Approved | JOSE AVILA |
| Service/Power Release | 8/2/2023 | Approved | JOSE AVILA |
| Final | 8/8/2023 | OK to Issue CofO | JOSE AVILA |