858 1/2 W 47TH PL 90037
Certificate Information: 858 1/2 W 47TH PL 90037
- Application / Permit
- 22010-20000-02369
- Plan Check / Job No.
- B22VN07130
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY DETACHED 2-UNIT ADU.
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Current Status
- CofO Issued on 7/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | JOE VO |
| Corrections Issued | 5/28/2022 | JOE VO |
| Quality Review Completed | 6/16/2022 | MICHAEL PEREZ |
| Applicant returned to address corrections | 9/5/2023 | JOE VO |
| Applicant returned to address corrections | 10/17/2023 | JOE VO |
| Plan Check Approved | 11/27/2023 | JOE VO |
| Plan Check Approved | 2/29/2024 | JOE VO |
| Issued | 9/16/2024 | APPLICANT |
| CofO in Progress | 7/14/2025 | BARRY HACHE |
| CofO in Progress | 7/14/2025 | BARRY HACHE |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
| CofO Issued | 7/20/2025 | DEROLD HAUFF |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2022 | CINDY QI |
| Sewer availability | Cleared | 7/21/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2022 | CINDY QI |
| Miscellaneous | Cleared | 7/27/2022 | CINDY QI |
| Permit | Cleared | 7/27/2022 | CINDY QI |
| Low Impact Development | Cleared | 9/2/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/6/2022 | CINDY QI |
| Construction near power lines | Cleared | 2/21/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/25/2024 | Corrections Issued | CRAIG DAVIS |
| Underground Mechanical | 11/26/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 12/13/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 12/17/2024 | Approved | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 1/21/2025 | Conditional Approval | BARRY HACHE |
| Deputy Wood Construction | 1/21/2025 | Conditional Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 2/28/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 2/28/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 3/3/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 3/3/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 3/5/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 3/5/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 3/5/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 3/6/2025 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 3/6/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 3/6/2025 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 3/10/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 3/10/2025 | Approved | BARRY HACHE |
| Insulation | 3/12/2025 | Approved | BARRY HACHE |
| Shower Pan | 3/12/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 3/18/2025 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 3/24/2025 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 3/26/2025 | Approved | BARRY HACHE |
| Sewer | 4/9/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 4/9/2025 | Approved | BARRY HACHE |
| Service/Power Release | 5/2/2025 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 5/2/2025 | Approved | BARRY HACHE |
| Final | 6/9/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 6/9/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 6/9/2025 | Not Ready for Inspection | BARRY HACHE |
| Drywall Nailing | 6/27/2025 | Approved | BARRY HACHE |
| Final | 6/27/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 6/27/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 6/27/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Required | BARRY HACHE |
| Service/Power Release | 6/27/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 6/27/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 7/2/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 7/2/2025 | Approved | JOSE MACIAS |
| Service/Power Release | 7/2/2025 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 7/2/2025 | Approved | JOSE MACIAS |
| Final | 7/9/2025 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 7/9/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 7/11/2025 | Conditional Approval | BARRY HACHE |
| Service/Power Release | 7/11/2025 | Approved | BARRY HACHE |