7432 N COLLETT AVE 91406

Certificate Information: 7432 N COLLETT AVE 91406

Application / Permit
22010-20000-02367
Plan Check / Job No.
B22VN07129
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT AND EXPAND (E) GARAGE INTO A.D.U. PER STATE LAW.
Permit Issued
Issued on 2/28/2023
Issuing Office
Current Status
CofO Issued on 11/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2022 APPLICANT
Assigned to Plan Check Engineer 5/18/2022 LAWRENCE QUIRANTE
Corrections Issued 5/19/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 7/9/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 8/18/2022 SHANGQIN XIE
Applicant returned to address corrections 12/1/2022 RAHEL BEYENE
Applicant returned to address corrections 1/26/2023 SAMUEL GONZALEZ
Applicant returned to address corrections 2/17/2023 RICARDO RAMIREZ
Plan Check Approved 2/26/2023 ZAW HAN
Issued 2/28/2023 APPLICANT
CofO in Progress 10/24/2023 RAUL OLAGI
CofO Issued 11/28/2023 RUBEN SALAS
Permit Finaled 11/28/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/18/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 10/18/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 10/20/2022 ROMAN GUTIERREZ
Sewer availability Cleared 10/20/2022 ROMAN GUTIERREZ

Contact Information

Contractor Reds General Construction Inc; Lic. No.: 1061700-B       ,
Engineer Aguilera,, Leo Avalos; Lic. No.: C31397 20644 OLEANDER AVENUE      PERRIS, CA 92320

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/16/2023 Corrections Issued RAUL OLAGI
Underground Mechanical 3/16/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/28/2023 Partial Approval RAUL OLAGI
Sewer 3/28/2023 Approved RAUL OLAGI
Underground Mechanical 3/28/2023 Approved RAUL OLAGI
Deputy Drilled-In Anchors 4/4/2023 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/4/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 4/4/2023 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/10/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 4/10/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/1/2023 Corrections Issued RAUL OLAGI
Green Building Rough 6/1/2023 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 6/1/2023 Approved RAUL OLAGI
Special/Order Compliance 6/1/2023 Corrections Issued RAUL OLAGI
Deputy Wood Construction 6/2/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Approved DAVID MATSON
BUILDING-Rough-Frame 6/21/2023 Approved RAUL OLAGI
Insulation 6/21/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 6/21/2023 Partial Approval RAUL OLAGI
Shower Pan 6/21/2023 Approved RAUL OLAGI
Drywall Nailing 6/26/2023 Approved RAUL OLAGI
ELECTRICAL-Final 9/5/2023 Corrections Issued RAUL OLAGI
Final 9/5/2023 Corrections Issued RAUL OLAGI
Green Building Final 9/5/2023 Approved RAUL OLAGI
HVAC-Final 9/5/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 9/5/2023 Corrections Issued RAUL OLAGI
Smoke Detectors 9/5/2023 Approved RAUL OLAGI
ELECTRICAL-Final 9/26/2023 Corrections Issued RAUL OLAGI
Final 9/26/2023 Corrections Issued RAUL OLAGI
HVAC-Final 9/26/2023 Approved RAUL OLAGI
PLUMBING-Final 9/26/2023 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Not Ready RAUL OLAGI
ELECTRICAL-Final 9/29/2023 Approved RAUL OLAGI
Final 9/29/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 9/29/2023 Corrections Issued RAUL OLAGI
Final 10/23/2023 OK to Issue CofO RAUL OLAGI
PLUMBING-Final 10/23/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Approved RAUL OLAGI