7914 N SATSUMA AVE 91352
Certificate Information: 7914 N SATSUMA AVE 91352
- Application / Permit
- 22010-20000-02354
- Plan Check / Job No.
- B22VN07121
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 2 STORY ADU 1,200 SQ FT
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- CofO Issued on 6/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 6/13/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 6/29/2022 | PETER KIM |
| Applicant returned to address corrections | 12/15/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/6/2024 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/15/2024 | ARMEN JIVALAGIAN |
| Plan Check Approved | 6/4/2024 | ARMEN JIVALAGIAN |
| Issued | 6/5/2024 | APPLICANT |
| CofO in Progress | 12/4/2025 | MATTHEW NELSON |
| CofO in Progress | 1/5/2026 | MATTHEW NELSON |
| CofO in Progress | 6/12/2026 | RAUL OLAGI |
| Permit Finaled | 6/17/2026 | RUBEN SALAS |
| CofO Issued | 6/17/2026 | RUBEN SALAS |
| Permit Finaled | 6/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/14/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 6/5/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 6/9/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/28/2024 | Corrections Issued | MATTHEW NELSON |
| Pre-Inspection | 7/3/2024 | Partial Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/20/2024 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 10/7/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/13/2024 | Partial Approval | DAVID MATSON |
| PLUMBING-Rough | 11/13/2024 | Approved | DAVID MATSON |
| Shower Pan | 12/11/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 12/11/2024 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/3/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 1/3/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 1/3/2025 | Approved | MATTHEW NELSON |
| Insulation | 1/14/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/14/2025 | Partial Approval | MATTHEW NELSON |
| Insulation | 1/23/2025 | Approved | MATTHEW NELSON |
| Deck | 2/4/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 3/19/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/25/2025 | Approved | MATTHEW NELSON |
| Underground Mechanical | 5/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 7/28/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 7/30/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 9/12/2025 | Approved | MATTHEW NELSON |
| HVAC-Final | 9/12/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 11/4/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 11/4/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Service/Power Release | 11/18/2025 | Corrections Issued | MATTHEW NELSON |
| Final | 12/3/2025 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/3/2025 | Approved | MATTHEW NELSON |
| HVAC-Final | 12/3/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/3/2025 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 12/3/2025 | Approved | MATTHEW NELSON |
| Smoke Detectors | 12/3/2025 | Approved | MATTHEW NELSON |
| Final | 1/6/2026 | Corrections Issued | MATTHEW NELSON |
| Final | 6/12/2026 | OK to Issue CofO | RAUL OLAGI |