12034 W OTSEGO ST 91607

Certificate Information: 12034 W OTSEGO ST 91607

Application / Permit
22010-20000-02348
Plan Check / Job No.
B22VN07104
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. New 2-story single family dwelling with 2-car attached garage.
Permit Issued
Issued on 12/19/2022
Issuing Office
Current Status
Issued on 12/19/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 TU HUA
Corrections Issued 6/22/2022 TU HUA
Quality Review Completed 6/23/2022 CHAD DOI
Applicant returned to address corrections 11/30/2022 TU HUA
Applicant returned to address corrections 12/1/2022 TU HUA
Applicant returned to address corrections 12/15/2022 TU HUA
Applicant returned to address corrections 12/16/2022 TU HUA
Plan Check Approved 12/16/2022 TU HUA
Issued 12/19/2022 APPLICANT
CofO in Progress 11/3/2023 JOHN COLEMAN
CofO Issued-Status Void 1/17/2024 RUBEN SALAS
Permit Finaled-Status Void 1/17/2024 RUBEN SALAS
Re-Activate Permit 1/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/30/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/30/2022 MEGAN GODINEZ
Sewer availability Cleared 7/5/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 8/5/2022 KURT CORRAL
Specific Plan Cleared 8/30/2022 CORREY KITCHENS
ZI Cleared 8/30/2022 CORREY KITCHENS
Low Impact Development Cleared 10/26/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/27/2022 DAGOVERTO GUERRERO
Permit Cleared 11/17/2022 ROMAN GUTIERREZ
Trees in Parkway Cleared 11/22/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/25/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 2/3/2023 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 2/9/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval JACK KARGODORIAN
Pre-Inspection 3/8/2023 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 4/14/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 4/28/2023 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 4/28/2023 Approved JOHN COLEMAN
Green Building Rough 4/28/2023 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 4/28/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 4/28/2023 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 4/28/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 5/3/2023 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Approved JOHN COLEMAN
Green Building Rough 5/5/2023 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 5/5/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 5/5/2023 Partial Approval JOHN COLEMAN
Shower Pan 5/5/2023 Approved JOHN COLEMAN
Shower Pan 5/8/2023 Corrections Issued JACK KARGODORIAN
Insulation 5/12/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 5/12/2023 Partial Approval JACK KARGODORIAN
Drywall Nailing 5/19/2023 Approved JACK KARGODORIAN
Green Building Rough 5/19/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 9/12/2023 Not Ready for Inspection JUAN VALENZUELA
Final 9/12/2023 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 9/12/2023 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 9/12/2023 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 9/12/2023 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 9/12/2023 Not Ready for Inspection JUAN VALENZUELA
Service/Power Release 9/14/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 10/20/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/20/2023 Approved JUAN VALENZUELA
Final 10/20/2023 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 10/20/2023 Approved JUAN VALENZUELA
Green Building Final 10/20/2023 Approved JUAN VALENZUELA
HVAC-Final 10/20/2023 Approved JUAN VALENZUELA
PLUMBING-Final 10/20/2023 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved JUAN VALENZUELA
Service/Power Release 10/20/2023 Approved JUAN VALENZUELA
Smoke Detectors 10/20/2023 Approved JUAN VALENZUELA
Final 11/3/2023 OK to Issue CofO JOHN COLEMAN