16231 W PARTHENIA ST 91343

Certificate Information: 16231 W PARTHENIA ST 91343

Application / Permit
22010-20000-02334
Plan Check / Job No.
B22VN07019
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ ATTACHED PATIO COVER
Permit Issued
Issued on 9/13/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 NILOOFAR MEHRAIN
Corrections Issued 6/2/2022 NILOOFAR MEHRAIN
Quality Review Completed 6/7/2022 STEVEN KIM
Building Plans Picked Up 6/9/2022 APPLICANT
Plan Check Approved 9/13/2022 NILOOFAR MEHRAIN
Issued 9/13/2022 APPLICANT
CofO in Progress 4/10/2024 RAUL OLAGI
Permit Finaled 4/23/2024 RUBEN SALAS
CofO Issued 4/23/2024 RUBEN SALAS
Permit Finaled 4/23/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/18/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 7/20/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 7/20/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 8/13/2022 RUEL COLE
Low Impact Development Cleared 8/30/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/1/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/27/2023 Partial Approval RAUL OLAGI
Sewer 4/27/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 5/25/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 6/1/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 6/6/2023 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Partial Approval RAUL OLAGI
Verify Sprinkler Sign Off 8/29/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 9/13/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 9/25/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 10/2/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 10/2/2023 Approved RAUL OLAGI
Green Building Rough 10/2/2023 Approved RAUL OLAGI
HVAC-Rough 10/2/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 10/2/2023 Partial Approval RAUL OLAGI
Insulation 10/13/2023 Approved RAUL OLAGI
Insulation 10/14/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 10/25/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 11/16/2023 Partial Approval RAUL OLAGI
Shower Pan 11/21/2023 Approved RAUL OLAGI
Underground Mechanical 11/21/2023 Approved RAUL OLAGI
ELECTRICAL-Final 1/16/2024 Not Ready for Inspection RAUL OLAGI
Final 3/8/2024 Corrections Issued RAUL OLAGI
Green Building Final 3/8/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready RAUL OLAGI
Service/Power Release 3/8/2024 Not Ready for Inspection RAUL OLAGI
Smoke Detectors 3/8/2024 Approved RAUL OLAGI
ELECTRICAL-Final 3/20/2024 Approved RAUL OLAGI
HVAC-Final 3/20/2024 Approved RAUL OLAGI
PLUMBING-Final 3/20/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Approved RAUL OLAGI
Final 4/10/2024 OK to Issue CofO RAUL OLAGI
Service/Power Release 4/10/2024 Approved RAUL OLAGI