4465 N KATHERINE AVE 91423

Certificate Information: 4465 N KATHERINE AVE 91423

Application / Permit
22010-20000-02332
Plan Check / Job No.
B22VN07012
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD, (2812 SQFT) W/ ATTACHED 2 CAR GARAGE (350 SQFT), (69'-6"x39'-0") W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/26/2022
Issuing Office
Current Status
CofO Issued on 5/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 PETER MOSESIAN
Corrections Issued 5/21/2022 PETER MOSESIAN
Quality Review Completed 5/26/2022 OMID HEDAYAT
Building Plans Picked Up 6/2/2022 APPLICANT
Applicant returned to address corrections 7/17/2022 PETER MOSESIAN
Plan Check Approved 8/23/2022 PETER MOSESIAN
Issued 8/26/2022 APPLICANT
CofO in Progress 5/26/2023 JOHN COLEMAN
CofO Issued 5/26/2023 MICHAEL SMITH
Permit Finaled 5/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Permit Cleared 5/23/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/24/2022 LEE GUILBEAUX
Sewer availability Cleared 5/24/2022 LEE GUILBEAUX
ZI Cleared 6/1/2022 NELSON RODRIGUEZ
Trees in Parkway Cleared 6/17/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 6/21/2022 MATTHEW CRAIG
Low Impact Development Cleared 8/5/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/8/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/19/2022 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 9/29/2022 Approved MISAEL ESPARZA
Footing/Foundation/Slab 9/29/2022 Approved MISAEL ESPARZA
Deputy Drilled-In Anchors 10/3/2022 Conditional Approval MISAEL ESPARZA
Deputy Reinf. Concrete 10/3/2022 Conditional Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Approved CALEB MEISTER
Wood Frame 10/11/2022 Partial Approval CALEB MEISTER
Deputy Steel/Welding 10/17/2022 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/31/2022 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 11/3/2022 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 11/4/2022 Approved MISAEL ESPARZA
Wood Frame 11/4/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 11/8/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 11/14/2022 Corrections Issued MISAEL ESPARZA
Shower Pan 11/22/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 12/1/2022 Approved MISAEL ESPARZA
HVAC-Rough 12/1/2022 Approved MISAEL ESPARZA
Wood Frame 12/1/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/7/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/7/2022 Approved MISAEL ESPARZA
Insulation 12/13/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/13/2022 Approved MATTHEW NELSON
Drywall Nailing 12/20/2022 Conditional Approval MISAEL ESPARZA
Green Building Rough 12/20/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/15/2023 Conditional Approval ROBERT GOLD
Drywall Nailing 5/15/2023 Approved ROBERT GOLD
ELECTRICAL-Final 5/15/2023 Not Ready for Inspection ROBERT GOLD
Final 5/15/2023 Corrections Issued ROBERT GOLD
Green Building Final 5/15/2023 Approved ROBERT GOLD
HVAC-Final 5/15/2023 Not Ready for Inspection ROBERT GOLD
MERV13>=Final 5/15/2023 Not Ready for Inspection ROBERT GOLD
MERV13>=Rough 5/15/2023 Partial Inspection ROBERT GOLD
PLUMBING-Final 5/15/2023 Corrections Issued ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved ROBERT GOLD
Service/Power Release 5/15/2023 Not Ready for Inspection ROBERT GOLD
Smoke Detectors 5/15/2023 Approved ROBERT GOLD
Verify Sprinkler Sign Off 5/15/2023 Approved ROBERT GOLD
BUILDING-Rough-Frame 5/23/2023 Approved JOHN COLEMAN
ELECTRICAL-Final 5/23/2023 Approved JOHN COLEMAN
Final 5/23/2023 Partial Inspection JOHN COLEMAN
HVAC-Final 5/23/2023 Approved JOHN COLEMAN
MERV13>=Final 5/23/2023 Approved JOHN COLEMAN
MERV13>=Rough 5/23/2023 Approved JOHN COLEMAN
PLUMBING-Final 5/23/2023 Approved JOHN COLEMAN
Service/Power Release 5/23/2023 Not Ready for Inspection JOHN COLEMAN
Final 5/26/2023 OK to Issue CofO JOHN COLEMAN
Service/Power Release 5/26/2023 Approved JOHN COLEMAN