5409-5409 1/2 S BUDLONG AVE 90037

Certificate Information: 5409-5409 1/2 S BUDLONG AVE 90037

Application / Permit
22010-20000-02294
Plan Check / Job No.
B22VN06878
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan : Convert Existing 2 Bedroom of an Existing Single Family Dwelling to an Accessory Dwelling Unit (393. sq. ft.) per PER CA GOVT CODE 65852.2(e)(1)(A)
Permit Issued
Issued on 6/15/2022
Issuing Office
Current Status
CofO Issued on 5/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 HANS SANTIAGO
Corrections Issued 5/13/2022 HANS SANTIAGO
Applicant returned to address corrections 6/8/2022 HANS SANTIAGO
Plan Check Approved 6/13/2022 ANDREW SANTIAGO
Issued 6/15/2022 APPLICANT
CofO in Progress 4/24/2025 SABAS ALONSO
No Progress 4/27/2025 DEROLD HAUFF
CofO in Progress 4/27/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF
CofO Issued 5/3/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/2/2022 CELINA MORENO
Sewer availability Cleared 6/2/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/3/2022 CELINA MORENO

Contact Information

Contractor Palos Verdes Construction; Lic. No.: 632133-B       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/14/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 12/18/2024 Not Ready for Inspection BARRY HACHE
HVAC-Rough 12/18/2024 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 12/18/2024 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 12/23/2024 Corrections Issued BARRY HACHE
Insulation 12/23/2024 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 12/27/2024 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Not Ready for Inspection BARRY HACHE
Insulation 12/27/2024 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 12/27/2024 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 1/6/2025 Corrections Issued BARRY HACHE
HVAC-Rough 1/6/2025 Corrections Issued BARRY HACHE
Insulation 1/6/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 1/6/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 1/15/2025 Corrections Issued BARRY HACHE
HVAC-Rough 1/15/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 1/15/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 1/16/2025 Not Ready for Inspection SABAS ALONSO
Final 1/16/2025 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 1/16/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 3/11/2025 Corrections Issued SABAS ALONSO
Green Building Rough 3/11/2025 Approved SABAS ALONSO
HVAC-Rough 3/11/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 3/26/2025 Not Ready for Inspection BARRY HACHE
Final 3/26/2025 Not Ready for Inspection BARRY HACHE
HVAC-Rough 3/26/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 4/4/2025 Approved SABAS ALONSO
HVAC-Rough 4/4/2025 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 4/8/2025 Approved SABAS ALONSO
HVAC-Final 4/8/2025 Approved SABAS ALONSO
Insulation 4/8/2025 Approved SABAS ALONSO
Drywall Nailing 4/15/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 4/15/2025 Approved SABAS ALONSO
Final 4/23/2025 OK to Issue CofO SABAS ALONSO
Smoke Detectors 4/23/2025 Approved SABAS ALONSO