4755-4757 N CLYBOURN AVE 91602

Certificate Information: 4755-4757 N CLYBOURN AVE 91602

Application / Permit
22010-20000-02293
Plan Check / Job No.
B22VN06877
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE 14'-6"X81' ONE STORY TWO UNIT ACCESSORY DWELLING UNIT [PER GCS 65852.2(e)(1)(D) AND LAMC 12.22A33(c), (d), and (g)]_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 4/24/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 DAWN MC NULTY
Corrections Issued 6/13/2022 DAWN MC NULTY
Quality Review Completed 6/22/2022 STEVEN KIM
Building Plans Picked Up 6/24/2022 APPLICANT
Green Plans Picked Up 6/24/2022 APPLICANT
Applicant returned to address corrections 2/1/2023 DAWN MC NULTY
Applicant returned to address corrections 6/7/2023 DAWN MC NULTY
Applicant returned to address corrections 7/24/2023 DAWN MC NULTY
Applicant returned to address corrections 11/2/2023 DAWN MC NULTY
Plan Check Approved 1/16/2024 DAWN MC NULTY
Issued 4/24/2024 APPLICANT
CofO in Progress 7/30/2025 JUAN VALENZUELA
Permit Finaled 8/18/2025 RUBEN SALAS
CofO Issued 8/18/2025 RUBEN SALAS
Permit Finaled 8/18/2025 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 1/11/2023 KEVIN FULTON
Address approval Cleared 1/18/2023 MEGAN GODINEZ
Highway dedication Cleared 1/18/2023 MEGAN GODINEZ
Tenant Habitability Plan Cleared 1/26/2023 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 6/7/2023 MEGAN GODINEZ
Sewer availability Cleared 6/9/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 10/10/2023 KURT CORRAL
Green Code Cleared 11/2/2023 MICHAEL AYERS
Low Impact Development (LID) Cleared 1/3/2024 ERNEST TSE

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/12/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 9/20/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Pre-Inspection 9/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 9/20/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/23/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Pre-Inspection 10/23/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 11/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/14/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/14/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 11/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 11/14/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 11/22/2024 Approved JOSE AVILA
PLUMBING-Rough 11/22/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 11/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 11/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 11/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 11/26/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Insulation 12/4/2024 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 12/4/2024 Corrections Issued MICHAEL CORTEZ
Insulation 12/9/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 12/13/2024 Approved RAUL OLAGI
ELECTRICAL-Final 5/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 5/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 5/16/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/16/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 5/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 5/21/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/23/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 6/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 6/23/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Green Building Final 6/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 6/26/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/30/2025 OK to Issue CofO JUAN VALENZUELA