7110 1/2 W VALMONT ST 91042

Certificate Information: 7110 1/2 W VALMONT ST 91042

Application / Permit
22010-20000-02267
Plan Check / Job No.
B22VN06803
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32' X 28'10" ACCESSORY DWELLING UNIT PER Ordinance LAMC 12.22 A.33 (c)-(d) "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 4/5/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 PINANK PATEL
Corrections Issued 5/8/2022 PINANK PATEL
Applicant returned to address corrections 11/10/2022 DANIEL SANJUAN
Applicant returned to address corrections 12/2/2022 KHUONG TRUONG
Applicant returned to address corrections 1/12/2023 KHUONG TRUONG
Plan Check Approved 3/23/2023 MINA HABILI
Issued 4/5/2023 APPLICANT
CofO in Progress 11/3/2023 WILLIAM WREN
Permit Finaled 11/25/2023 RUBEN SALAS
CofO Issued 11/25/2023 RUBEN SALAS
Permit Finaled 11/25/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/14/2022 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 6/15/2022 CHRIS CHAHBAZ
Grading Pre-Inspection Cleared 6/15/2022 KIRK LINKLATER
Sewer availability Cleared 6/15/2022 CHRIS CHAHBAZ
Roof/Waste drainage to street Cleared 7/6/2022 CHRIS CHAHBAZ
Hydrant and Access approval Cleared 9/13/2022 GILBERT URREA
Specific Plan Cleared 10/12/2022 SARAH HOUNSELL
ZI Cleared 10/12/2022 SARAH HOUNSELL
GPI Written Notices Cleared 12/2/2022 PINANK PATEL

Contact Information

Contractor Design Pro & Starlite Inc; Lic. No.: 948621-B 2951 HONOLULU AVENUE UNIT F      LA CRESCENTA, CA 91214
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/20/2023 Approved WILLIAM WREN
Footing/Foundation/Slab 4/20/2023 Approved WILLIAM WREN
PLUMBING-Rough 5/3/2023 Partial Approval WILLIAM WREN
Wood Frame 5/3/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/10/2023 Partial Approval WILLIAM WREN
Insulation 5/10/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 6/6/2023 Approved WILLIAM WREN
PLUMBING-Rough 6/6/2023 Approved WILLIAM WREN
Sewer 6/6/2023 Approved WILLIAM WREN
Underground Mechanical 6/6/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/13/2023 Approved WILLIAM WREN
Green Building Rough 6/13/2023 Approved WILLIAM WREN
HVAC-Rough 6/13/2023 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 6/13/2023 Partial Approval WILLIAM WREN
Shower Pan 6/13/2023 Approved WILLIAM WREN
Verify Sprinkler Sign Off 6/13/2023 Approved WILLIAM WREN
Insulation 6/15/2023 Corrections Issued WILLIAM WREN
Drywall Nailing 6/26/2023 Approved WILLIAM WREN
HVAC-Rough 6/26/2023 Approved WILLIAM WREN
Insulation 6/26/2023 Approved WILLIAM WREN
Final 10/3/2023 Corrections Issued WILLIAM WREN
Green Building Final 10/3/2023 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Not Ready WILLIAM WREN
Service/Power Release 10/3/2023 Approved WILLIAM WREN
Smoke Detectors 10/3/2023 Approved WILLIAM WREN
Final 10/16/2023 OK to Issue CofO WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Approved WILLIAM WREN