10807 W VALERIO ST 91352
Certificate Information: 10807 W VALERIO ST 91352
- Application / Permit
- 22010-20000-02254
- Plan Check / Job No.
- B22VN06787
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW SB9 UNIT PER TWO UNIT DEVELOPMENT SB9
- Permit Issued
- Issued on 3/8/2023
- Issuing Office
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | CARLOS MONTES |
| Corrections Issued | 7/7/2022 | CARLOS MONTES |
| Quality Review Completed | 7/20/2022 | GARO TELMI |
| Applicant returned to address corrections | 1/12/2023 | CARLOS MONTES |
| Plan Check Approved | 3/8/2023 | CARLOS MONTES |
| Issued | 3/8/2023 | APPLICANT |
| CofO in Progress | 4/12/2024 | JOHN HAYES |
| No Progress | 5/13/2024 | ROBERT GOLD |
| CofO in Progress | 5/13/2024 | ROBERT GOLD |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
| CofO Issued | 5/15/2024 | RUBEN SALAS |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 9/30/2022 | GILBERT URREA |
| Sewer availability | Cleared | 10/5/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 1/11/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/24/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: NA56881 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/27/2023 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 4/27/2023 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 5/5/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/10/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 7/10/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/10/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 7/19/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 7/19/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/19/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/19/2023 | Approved | JOHN HAYES |
| Special/Order Compliance | 7/19/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/25/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 8/25/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/25/2023 | Partial Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 8/25/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/14/2023 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 9/14/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 9/28/2023 | Partial Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 9/28/2023 | Approved | JOHN HAYES |
| Insulation | 10/2/2023 | Approved | JOHN HAYES |
| Insulation | 10/3/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/6/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/6/2023 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 10/6/2023 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 10/18/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/13/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 3/15/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 3/15/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 3/15/2024 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 3/15/2024 | Approved | JOHN HAYES |
| Final | 3/21/2024 | Corrections Issued | JOHN HAYES |
| Service/Power Release | 3/21/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 3/28/2024 | Corrections Issued | JOHN HAYES |
| Service/Power Release | 3/28/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 4/12/2024 | OK to Issue CofO | JOHN HAYES |
| Service/Power Release | 4/12/2024 | Approved | JOHN HAYES |