6232 N MORELLA AVE 91606

Certificate Information: 6232 N MORELLA AVE 91606

Application / Permit
22010-20000-02235
Plan Check / Job No.
B22VN06715
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: New ADU 2-story ground floor addition and 2nd story addition over (E) 1-story garage.
Permit Issued
Issued on 8/1/2023
Issuing Office
Current Status
CofO Issued on 2/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 KELVIN CHUONG
Corrections Issued 6/15/2022 KELVIN CHUONG
Quality Review Completed 6/15/2022 RODOLFO ARIAS
Applicant returned to address corrections 10/13/2022 KELVIN CHUONG
Applicant returned to address corrections 11/1/2022 KELVIN CHUONG
Applicant returned to address corrections 11/9/2022 KELVIN CHUONG
Applicant returned to address corrections 3/31/2023 KELVIN CHUONG
Plan Check Approved 7/18/2023 KELVIN CHUONG
Issued 8/1/2023 APPLICANT
CofO in Progress 9/2/2025 JOSE AVILA
Permit Finaled 2/18/2026 RUBEN SALAS
CofO Issued 2/18/2026 RUBEN SALAS
Permit Finaled 2/18/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/13/2022 ROMAN GUTIERREZ
Street width determination Cleared 7/13/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/15/2022 ROMAN GUTIERREZ
Sewer availability Cleared 7/15/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 2/27/2023 RIDWAN HARDY
Construction near power lines Cleared 2/27/2023 RIDWAN HARDY
Low Impact Development Cleared 6/20/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 7/5/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/13/2023 Partial Approval JOHN HAYES
Underground Mechanical 11/13/2023 Approved JOHN HAYES
PLUMBING-Rough 11/16/2023 No Access for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 12/1/2023 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 12/19/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 12/26/2023 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 12/29/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/4/2024 Approved RYAN SALAZAR
Deputy Reinf. Concrete 1/5/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 5/3/2024 Partial Approval JOHN COLEMAN
Green Building Rough 5/3/2024 Not Ready for Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/6/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 6/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/20/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 6/28/2024 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 7/18/2024 Approved JOSE AVILA
ELECTRICAL-Rough 7/25/2024 Approved JOSE AVILA
Deputy Wood Construction 7/26/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 8/6/2024 Approved VINCENT HANLEY
Green Building Rough 8/6/2024 Approved VINCENT HANLEY
HVAC-Rough 8/6/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/6/2024 Partial Approval VINCENT HANLEY
Insulation 8/9/2024 Corrections Issued MICHAEL CORTEZ
Insulation 8/16/2024 Approved JOSE AVILA
Drywall Nailing 8/23/2024 Approved JOSE AVILA
Interior/Exterior Lathing 9/30/2024 Approved JOSE AVILA
Sewer 10/25/2024 Approved JOSE AVILA
Underground Mechanical 10/25/2024 Approved JOSE AVILA
Special/Order Compliance 1/7/2025 Approved JOSE AVILA
Final 1/31/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 1/31/2025 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/31/2025 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 1/31/2025 Approved MISAEL ESPARZA
Final 7/15/2025 Not Ready for Inspection JOSE AVILA
Final 8/1/2025 OK to Issue CofO JOSE AVILA
Green Building Final 8/1/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Not Required JOSE AVILA