413 E 43RD ST 90011
Certificate Information: 413 E 43RD ST 90011
- Application / Permit
- 22010-20000-02214
- Plan Check / Job No.
- B22VN06655
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW DETACHED ADU. SLAB ON GRADE. 498 SQUARE FEET 23'X21'-8" PER STATE LAW ALL WORK DONE PER WFPP ***Code Enforcement Bureau has issued an order. This parcel is eligible for issuance of a 30 day time limit permit (including Building, Electrical, HVAC and Plumbing) with a work description as follows. "COMPLY WITH DEPARTMENT ORDER effective date 11/12/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector MEL KHACHATOURIAN at (213)978-4494 of GENERAL ENFORCEMENT SOUTH. CEIS Case Number is 901568.***
- Permit Issued
- Issued on 10/15/2022
- Issuing Office
- Current Status
- Issued on 10/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | KHUONG TRUONG |
| Corrections Issued | 5/13/2022 | KHUONG TRUONG |
| Plan Check Approved | 8/10/2022 | KHUONG TRUONG |
| Issued | 10/15/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 6/10/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/30/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/1/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 2/14/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Underground Mechanical | 2/14/2023 | Corrections Issued | MARIO CUEVAS |
| Underground Mechanical | 2/17/2023 | Corrections Issued | MARIO CUEVAS |
| Underground Mechanical | 2/22/2023 | Approved | MARIO CUEVAS |
| Footing/Foundation/Slab | 2/24/2023 | Approved | MARIO CUEVAS |
| BUILDING-Rough-Frame | 3/10/2023 | Corrections Issued | MARIO CUEVAS |
| Green Building Rough | 3/10/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Verify Sprinkler Sign Off | 3/10/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Wood Frame | 3/10/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Wood Frame | 3/17/2023 | Corrections Issued | MARIO CUEVAS |
| BUILDING-Rough-Frame | 5/5/2023 | Not Ready for Inspection | MARIO CUEVAS |
| ELECTRICAL-Rough | 5/5/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Green Building Rough | 5/5/2023 | Not Ready for Inspection | MARIO CUEVAS |
| HVAC-Rough | 5/5/2023 | Not Ready for Inspection | MARIO CUEVAS |
| PLUMBING-Rough | 5/5/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Verify Sprinkler Sign Off | 5/5/2023 | Not Ready for Inspection | MARIO CUEVAS |
| BUILDING-Rough-Frame | 5/17/2023 | Corrections Issued | MARIO CUEVAS |
| ELECTRICAL-Rough | 5/17/2023 | Corrections Issued | MARIO CUEVAS |
| Green Building Rough | 5/17/2023 | Not Ready for Inspection | MARIO CUEVAS |
| PLUMBING-Rough | 5/17/2023 | Corrections Issued | MARIO CUEVAS |
| Verify Sprinkler Sign Off | 5/17/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Wood Frame | 5/17/2023 | Not Ready for Inspection | MARIO CUEVAS |
| BUILDING-Rough-Frame | 5/23/2023 | Corrections Issued | MARIO CUEVAS |
| ELECTRICAL-Rough | 5/23/2023 | Corrections Issued | MARIO CUEVAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Approved | MARIO CUEVAS |
| Green Building Rough | 5/23/2023 | Not Ready for Inspection | MARIO CUEVAS |
| HVAC-Rough | 5/23/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Verify Sprinkler Sign Off | 5/23/2023 | Not Ready for Inspection | MARIO CUEVAS |
| BUILDING-Rough-Frame | 5/30/2023 | Conditional Approval | MARIO CUEVAS |
| ELECTRICAL-Rough | 5/30/2023 | Approved | MARIO CUEVAS |
| Green Building Rough | 5/30/2023 | Approved | MARIO CUEVAS |
| Insulation | 6/5/2023 | Approved | MARIO CUEVAS |
| Interior/Exterior Lathing | 6/5/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Drywall Nailing | 6/9/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Interior/Exterior Lathing | 6/9/2023 | Corrections Issued | MARIO CUEVAS |
| Drywall Nailing | 6/13/2023 | Approved | MARIO CUEVAS |
| Interior/Exterior Lathing | 6/13/2023 | Approved | MARIO CUEVAS |