702 1/2 E 87TH ST 90002
Certificate Information: 702 1/2 E 87TH ST 90002
- Application / Permit
- 22010-20000-02209
- Plan Check / Job No.
- B21VN18221
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** CONVERT EXISTING DETACHED "GARAGE AND STORAGE" BUILDING TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 12/27/2022
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | GEORGE ALVAREZ |
| Corrections Issued | 5/13/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 7/25/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 9/13/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 9/15/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 10/11/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 10/24/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 12/14/2022 | GEORGE ALVAREZ |
| Issued | 12/27/2022 | APPLICANT |
| CofO in Progress | 9/12/2023 | MICHAEL LEWIS |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/12/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2022 | WALLIE JONG |
| Address approval | Cleared | 12/1/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 4/7/2023 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/11/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/8/2023 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/8/2023 | Corrections Issued | MICHAEL LEWIS |
| Deputy Wood Construction | 5/12/2023 | Conditional Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/15/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 6/1/2023 | Conditional Approval | MICHAEL LEWIS |
| ELECTRICAL-Final | 6/13/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Insulation | 6/13/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 6/13/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/16/2023 | Approved | MICHAEL LEWIS |
| Final | 7/28/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 7/28/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 7/28/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 8/15/2023 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 8/15/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 8/15/2023 | Approved | MICHAEL LEWIS |
| Final | 9/11/2023 | OK to Issue CofO | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Approved | MICHAEL LEWIS |