960 E INDIANA AVE 90291
Certificate Information: 960 E INDIANA AVE 90291
- Application / Permit
- 22010-20000-02195
- Plan Check / Job No.
- B22VN06607
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 48' X 67-7" 2-STORY IRREGULAR SHAPED SFD W/ ATTACHED 2-CAR GARAGE AND ROOF TOP DECK. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | RAPHAEL ROSAS |
| Corrections Issued | 6/7/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 6/13/2022 | STEVEN KIM |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| Applicant returned to address corrections | 8/4/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 8/25/2022 | RAPHAEL ROSAS |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 10/24/2023 | HERBERT GIRON |
| Permit Finaled | 10/28/2023 | DANIEL ORRANTE |
| CofO Issued | 10/28/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2022 | DINAH GARIN |
| Permit | Cleared | 6/17/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2022 | DINAH GARIN |
| Sewer availability | Cleared | 6/23/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 6/24/2022 | MARCO SANCHEZ |
| Trees in Parkway | Cleared | 7/6/2022 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 7/12/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 7/29/2022 | LAVEON RIDER |
| Hold | Cleared | 9/29/2022 | PRISCILLA RUIZ |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2022 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 9/6/2022 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 9/8/2022 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 9/8/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 9/14/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 12/19/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/20/2022 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 1/18/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 1/20/2023 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 1/26/2023 | Approved | EVAN COOPER |
| Green Building Rough | 1/26/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/26/2023 | Approved | EVAN COOPER |
| Shower Pan | 1/26/2023 | Approved | EVAN COOPER |
| Grounding or Bonding | 6/13/2023 | Not Ready for Inspection | RICHARD STEINBACH |
| Final | 7/20/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 7/26/2023 | Corrections Issued | EVAN COOPER |
| Service/Power Release | 7/26/2023 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 8/4/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 8/4/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/11/2023 | Approved | EVAN COOPER |
| Final | 8/11/2023 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 8/11/2023 | Approved | EVAN COOPER |
| Green Building Final | 8/11/2023 | Approved | EVAN COOPER |
| HVAC-Final | 8/11/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/11/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 8/11/2023 | Approved | EVAN COOPER |
| Smoke Detectors | 8/11/2023 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 8/11/2023 | Approved | EVAN COOPER |
| Final | 8/24/2023 | Corrections Issued | HERBERT GIRON |
| Final | 9/6/2023 | Corrections Issued | HERBERT GIRON |
| Final | 10/23/2023 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 10/23/2023 | Approved | HERBERT GIRON |