Work Description
NEW 196-8" X 93'-4" WAREHOUSE BUILDING (4 Tenants) ALL WORK PER ENGINEERING TYPE IIIB CONSTRUCTION, NFPA 13 THROUGHOUT.
Permit Issued
Issued on 9/15/2023
Issuing Office
Valley
Current Status
Issued on 9/15/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 SEWADA ZADOORIAN MILAGARDI
Green Plans Picked Up 5/27/2022 APPLICANT
Corrections Issued 6/6/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 6/6/2022 OMID HEDAYAT
Building Plans Picked Up 6/8/2022 APPLICANT
Disabled Access Plans Picked Up 6/8/2022 APPLICANT
Applicant returned to address corrections 1/6/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/23/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 2/23/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/11/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 7/31/2023 SEWADA ZADOORAN MILAGARDI
Issued 9/15/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/16/2022 CARLOS AGUILERA
Sewer availability Cleared 6/16/2022 CARLOS AGUILERA
Trees in Parkway Cleared 6/28/2022 ADALBERTO VERA
ZA Case Cleared 8/18/2022 NATHAN ROMINE
Green Code Cleared 9/2/2022 MICHAEL AYERS
Clean Up Green Up Cleared 9/7/2022 NATHAN ROMINE
Prkng lot landscape/Water mgmt Cleared 9/7/2022 NATHAN ROMINE
DAS Clearance Cleared 9/8/2022 SEWADA ZADOORAN MILAGARDI
ZI Cleared 9/22/2022 NATHAN ROMINE
"Q" conditions Cleared 11/17/2022 NATHAN ROMINE
Low Impact Development Cleared 12/21/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/22/2022 CARLOS AGUILERA
Highway dedication Cleared 4/5/2023 LEE GUILBEAUX
Permit Cleared 6/12/2023 CARLOS AGUILERA
"T" removal Cleared 7/19/2023 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,
Engineer Kardjian,, Vahe Matios; Lic. No.: C40821 1112 W BURBANK BLVD STE 301      BURBANK, CA 91506
Engineer Sosnowski,, Christopher John; Lic. No.: C53660 2117 S. 48TH ST   SUITE 103    TEMPE, AZ 85281

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/7/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 12/12/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/14/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/15/2023 Approved DANNY RODRIGUEZ
Green Building Rough 12/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/15/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/18/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/19/2023 Approved DANNY RODRIGUEZ
Green Building Rough 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 12/19/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/19/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/20/2023 No Access for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/21/2023 No Access for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/26/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/27/2023 Approved DANNY RODRIGUEZ
Green Building Rough 12/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/27/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/28/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/29/2023 Conditional Approval JOHN KITCKO
Reinforced Concrete Frame 1/2/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/4/2024 Approved DANNY RODRIGUEZ
Green Building Rough 1/4/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 1/4/2024 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/4/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/5/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/8/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/9/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 1/10/2024 Approved DANNY RODRIGUEZ
Green Building Rough 1/10/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 1/10/2024 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/10/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 1/25/2024 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/25/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/25/2024 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 7/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/14/2025 Not Ready for Inspection DANNY RODRIGUEZ