7443 N AMESTOY AVE 91316

Certificate Information: 7443 N AMESTOY AVE 91316

Application / Permit
22010-20000-02154
Plan Check / Job No.
B22VN06505
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan New detached ADU At Rear of the Lot.
Permit Issued
Issued on 5/24/2023
Issuing Office
Current Status
CofO Corrected on 8/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/11/2022 MINA HABILI
Corrections Issued 5/12/2022 MINA HABILI
Plan Check Approved 1/30/2023 DANIEL SANJUAN
Issued 5/24/2023 APPLICANT
CofO in Progress 6/26/2024 RAUL OLAGI
Permit Finaled-Status Void 7/10/2024 RUBEN SALAS
CofO Issued-Status Void 7/10/2024 RUBEN SALAS
Re-Activate Permit 8/27/2024 RUBEN SALAS
Permit Finaled 8/27/2024 RUBEN SALAS
CofO Corrected 8/27/2024 RUBEN SALAS
Permit Finaled 8/27/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/30/2022 CARLOS AGUILERA
Construction near power lines Cleared 8/23/2022 RIDWAN HARDY
Sewer availability Cleared 8/29/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/5/2022 ROSE MARIE SMITH
Low Impact Development Cleared 11/2/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 12/7/2022 LEE GUILBEAUX

Contact Information

Contractor Robert Konstruction; Lic. No.: 985284-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766
Engineer Barakat,, Fouad Chafic; Lic. No.: NA67449       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/16/2023 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 7/25/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 7/25/2023 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 8/9/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 8/9/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 10/26/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 10/26/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 10/26/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 10/26/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 10/26/2023 Corrections Issued RAUL OLAGI
Sewer 10/26/2023 Approved RAUL OLAGI
Underground Mechanical 10/26/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/7/2023 Approved RAUL OLAGI
Green Building Rough 11/7/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 11/7/2023 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 11/7/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 11/7/2023 Approved RAUL OLAGI
Insulation 11/9/2023 Approved RAUL OLAGI
Drywall Nailing 11/20/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 11/20/2023 Approved JUAN VALENZUELA
Final 6/14/2024 Corrections Issued RAUL OLAGI
Green Building Final 6/14/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Not Ready RAUL OLAGI
Service/Power Release 6/14/2024 Not Ready for Inspection RAUL OLAGI
Smoke Detectors 6/14/2024 Approved RAUL OLAGI
Final 6/24/2024 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved RAUL OLAGI
Final 6/26/2024 OK to Issue CofO RAUL OLAGI
Service/Power Release 6/26/2024 Approved RAUL OLAGI