4928 S 8TH AVE 90043
Certificate Information: 4928 S 8TH AVE 90043
- Application / Permit
- 22010-20000-02144
- Plan Check / Job No.
- B22VN06473
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 32'-6"X33' TWO STORY SFD WITH ATTACHED 19'X19' TWO CAR GARAGE _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D. "COMPLY WITH DEPARTMENT ORDER effective date 03/17/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 12/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | DAWN MC NULTY |
| Corrections Issued | 5/16/2022 | DAWN MC NULTY |
| Quality Review Completed | 5/18/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| Applicant returned to address corrections | 10/5/2022 | DAWN MC NULTY |
| Applicant returned to address corrections | 10/27/2022 | DAWN MC NULTY |
| Plan Check Approved | 11/4/2022 | DAWN MC NULTY |
| Issued | 12/14/2022 | APPLICANT |
| CofO in Progress | 10/18/2023 | ANTHONY EGSON |
| CofO Issued | 11/2/2023 | DEROLD HAUFF |
| Permit Finaled | 11/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2022 | WALLIE JONG |
| Permit | Cleared | 5/23/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2022 | WALLIE JONG |
| Sewer availability | Cleared | 5/25/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 7/18/2022 | KURT CORRAL |
| Trees in Parkway | Cleared | 7/22/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 9/7/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/8/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 1/13/2023 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/27/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 3/8/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/9/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 3/28/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/3/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/3/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/10/2023 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 4/10/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 4/18/2023 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 4/26/2023 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 5/2/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/2/2023 | Partial Approval | ANTHONY EGSON |
| Insulation | 5/8/2023 | Approved | ANTHONY EGSON |
| Insulation | 5/11/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/17/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/17/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 7/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 7/3/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 8/18/2023 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 8/18/2023 | Corrections Issued | SCOTT FINNILA |
| Service/Power Release | 8/18/2023 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 8/25/2023 | Approved | STUART CHAPMAN |
| Green Building Final | 8/25/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 8/25/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 8/25/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/6/2023 | Approved | ANTHONY EGSON |
| Final | 9/6/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 9/6/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/6/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 9/6/2023 | Approved | ANTHONY EGSON |
| Smoke Detectors | 9/6/2023 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 9/6/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/8/2023 | SGSOV Approved | ANTHONY EGSON |
| Final | 10/17/2023 | OK to Issue CofO | ANTHONY EGSON |