10505 N ONEIDA AVE 91331

Certificate Information: 10505 N ONEIDA AVE 91331

Application / Permit
22010-20000-02139
Plan Check / Job No.
B22VN06448
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 26'-8" x 45'-6" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 1/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 JEROME MAGAT PALMA
Corrections Issued 6/4/2022 JEROME MAGAT PALMA
Building Plans Picked Up 6/7/2022 APPLICANT
Applicant returned to address corrections 1/9/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 1/12/2023 MIROOSH KHACHATOORIAN
Issued 1/12/2023 APPLICANT
CofO in Progress 2/12/2024 MICHEL ABAJAN
Permit Finaled 3/29/2024 RONALD MYRICK
CofO Issued 3/29/2024 RONALD MYRICK
Permit Finaled 3/29/2024 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 6/22/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 10/5/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/12/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 12/2/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/6/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 1/6/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Luisoni,, Antonio Stefano; Lic. No.: S1781 12757 DEON PLACE      GRANADA HILLS, CA 91344

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/23/2023 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 3/6/2023 Approved MICHEL ABAJAN
Footing/Foundation/Slab 3/6/2023 Conditional Approval MICHEL ABAJAN
METHANE-Barrier 3/6/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 3/6/2023 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 3/14/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 4/25/2023 Approved MICHEL ABAJAN
Green Building Rough 4/25/2023 Approved MICHEL ABAJAN
METHANE-Rough 4/25/2023 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 4/25/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/25/2023 Approved MICHEL ABAJAN
Deputy Wood Construction 5/2/2023 Conditional Approval ROBERT GOLD
Insulation 5/15/2023 Approved MICHEL ABAJAN
Shower Pan 5/23/2023 Approved MICHEL ABAJAN
Drywall Nailing 5/30/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/30/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/5/2023 Approved MICHEL ABAJAN
Service/Power Release 8/15/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 8/18/2023 Not Ready for Inspection MICHEL ABAJAN
Final 8/18/2023 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 8/18/2023 Approved MICHEL ABAJAN
Green Building Final 8/18/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 8/18/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 8/18/2023 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 8/18/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 8/18/2023 Approved MICHEL ABAJAN
Pre-Inspection 8/23/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 9/28/2023 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Final 10/2/2023 Approved MICHEL ABAJAN
Final 10/2/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 10/2/2023 Approved MICHEL ABAJAN
HVAC-Final 10/2/2023 Approved MICHEL ABAJAN
PLUMBING-Final 10/2/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 10/2/2023 Not Ready for Inspection MICHEL ABAJAN
Pre-Inspection 10/23/2023 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 11/29/2023 Approved MICHEL ABAJAN
Final 12/20/2023 Corrections Issued MICHEL ABAJAN
Service/Power Release 12/20/2023 Not Ready for Inspection MICHEL ABAJAN
Final 2/12/2024 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 2/12/2024 Approved MICHEL ABAJAN