11249 N WISH AVE 91344
Certificate Information: 11249 N WISH AVE 91344
- Application / Permit
- 22010-20000-02124
- Plan Check / Job No.
- B22VN06375
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-0" X 24'-0" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g). WORK PER WFPP. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 8/18/2023
- Issuing Office
- Valley
- Current Status
- Issued on 8/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 5/4/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 6/7/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| Applicant returned to address corrections | 1/3/2023 | ROSENDO MEDINA |
| Plan Check Approved | 8/18/2023 | GIOVANNY CHAVEZ |
| Issued | 8/18/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/16/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 7/29/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 1/3/2023 | ARTIN ZARUKIAN |
| Grading Pre-Inspection | Cleared | 1/3/2023 | ARTIN ZARUKIAN |
| Construction near power lines | Cleared | 6/20/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/13/2024 | Partial Approval | STEVEN BACK |
| Special/Order Compliance | 2/13/2024 | Corrections Issued | STEVEN BACK |
| Pre-Inspection | 4/11/2024 | Partial Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/30/2024 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 5/30/2024 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 12/6/2024 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 12/6/2024 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 3/5/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/5/2025 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 3/5/2025 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 3/21/2025 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 3/21/2025 | Partial Approval | STEVEN BACK |
| Sewer | 3/21/2025 | Approved | STEVEN BACK |
| Underground Mechanical | 3/21/2025 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 4/3/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 4/3/2025 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 4/3/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | STEVEN BACK |
| Green Building Rough | 6/6/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 6/6/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/6/2025 | Not Ready for Inspection | STEVEN BACK |
| MERV13>=Rough | 6/6/2025 | Approved | STEVEN BACK |
| Insulation | 7/7/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 11/21/2025 | Approved | STEVEN BACK |
| Shower Pan | 11/21/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/8/2025 | Approved | KRISTEN CAUSEY |