22219 W VANOWEN ST 91303
Certificate Information: 22219 W VANOWEN ST 91303
- Application / Permit
- 22010-20000-02119
- Plan Check / Job No.
- B22VN06362
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: N) 2-Story ADU: 1,186 SF
- Permit Issued
- Issued on 5/19/2023
- Issuing Office
- Current Status
- CofO Issued on 9/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 6/21/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 7/1/2022 | FARUK SEZER |
| Plan Check Approved | 5/17/2023 | CRYSTEL MAALOUF |
| Issued | 5/19/2023 | APPLICANT |
| CofO in Progress | 8/27/2024 | GEVORK IPCHYAN |
| Permit Finaled | 9/23/2024 | JOHN JANSON |
| CofO Issued | 9/23/2024 | JOHN JANSON |
| Permit Finaled | 9/23/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/5/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/6/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 3/3/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/6/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/17/2024 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 1/17/2024 | Partial Approval | HORACE FULTZ |
| Footing/Foundation/Slab | 1/23/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 4/5/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 4/5/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Rough | 4/5/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/5/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 4/5/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 4/11/2024 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 4/11/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/11/2024 | Approved | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 4/11/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/19/2024 | Partial Approval | GEVORK IPCHYAN |
| Shower Pan | 4/19/2024 | Approved | GEVORK IPCHYAN |
| Insulation | 4/25/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/25/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 5/8/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 8/12/2024 | Approved | GEVORK IPCHYAN |
| Final | 8/12/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Service/Power Release | 8/12/2024 | Approved | GEVORK IPCHYAN |
| Smoke Detectors | 8/12/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 8/26/2024 | Approved | GEVORK IPCHYAN |
| Final | 8/26/2024 | OK to Issue CofO | GEVORK IPCHYAN |
| HVAC-Final | 8/26/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 8/26/2024 | Approved | GEVORK IPCHYAN |