22219 W VANOWEN ST 91303

Certificate Information: 22219 W VANOWEN ST 91303

Application / Permit
22010-20000-02119
Plan Check / Job No.
B22VN06362
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: N) 2-Story ADU: 1,186 SF
Permit Issued
Issued on 5/19/2023
Issuing Office
Current Status
CofO Issued on 9/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 CRYSTEL MAALOUF
Corrections Issued 6/21/2022 CRYSTEL MAALOUF
Quality Review Completed 7/1/2022 FARUK SEZER
Plan Check Approved 5/17/2023 CRYSTEL MAALOUF
Issued 5/19/2023 APPLICANT
CofO in Progress 8/27/2024 GEVORK IPCHYAN
Permit Finaled 9/23/2024 JOHN JANSON
CofO Issued 9/23/2024 JOHN JANSON
Permit Finaled 9/23/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/5/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/6/2022 CARLOS AGUILERA
Sewer availability Cleared 7/6/2022 CARLOS AGUILERA
Low Impact Development Cleared 3/3/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/6/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/17/2024 Not Ready for Inspection HORACE FULTZ
PLUMBING-Rough 1/17/2024 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 1/23/2024 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 4/5/2024 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 4/5/2024 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 4/5/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 4/5/2024 Not Ready for Inspection GEVORK IPCHYAN
Verify Sprinkler Sign Off 4/5/2024 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 4/11/2024 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Approved GEVORK IPCHYAN
HVAC-Rough 4/11/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 4/11/2024 Approved GEVORK IPCHYAN
Verify Sprinkler Sign Off 4/11/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 4/19/2024 Partial Approval GEVORK IPCHYAN
Shower Pan 4/19/2024 Approved GEVORK IPCHYAN
Insulation 4/25/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 4/25/2024 Approved GEVORK IPCHYAN
Drywall Nailing 5/8/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 8/12/2024 Approved GEVORK IPCHYAN
Final 8/12/2024 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 8/12/2024 SGSOV Approved GEVORK IPCHYAN
Service/Power Release 8/12/2024 Approved GEVORK IPCHYAN
Smoke Detectors 8/12/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Final 8/26/2024 Approved GEVORK IPCHYAN
Final 8/26/2024 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 8/26/2024 Approved GEVORK IPCHYAN
PLUMBING-Final 8/26/2024 Approved GEVORK IPCHYAN