4242 N ELMER AVE 91602
Certificate Information: 4242 N ELMER AVE 91602
- Application / Permit
- 22010-20000-02088
- Plan Check / Job No.
- B22VN06297
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 10' X 22'-8" DETACHED REC ROOM (SHOWER WITH EXTERIOR ACCESS ONLY). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | RAPHAEL ROSAS |
| Corrections Issued | 5/16/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 5/18/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| Applicant returned to address corrections | 8/9/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 9/7/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 9/21/2022 | RAPHAEL ROSAS |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 6/7/2023 | JACK KARGODORIAN |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
| CofO Issued | 6/8/2023 | MICHAEL SMITH |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 5/19/2022 | NELSON RODRIGUEZ |
| Sewer availability | Cleared | 5/24/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 6/14/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/29/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/25/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/5/2022 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/13/2022 | Approved | JACK KARGODORIAN |
| Pre-Inspection | 10/13/2022 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 10/13/2022 | Partial Approval | JACK KARGODORIAN |
| Pre-Inspection | 10/24/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 12/27/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/6/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 1/20/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 1/20/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 1/24/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/6/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 2/6/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 2/6/2023 | Approved | JACK KARGODORIAN |
| Insulation | 2/9/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 2/17/2023 | Approved | JACK KARGODORIAN |
| Final | 6/1/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 6/1/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Service/Power Release | 6/1/2023 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 6/1/2023 | Approved | JACK KARGODORIAN |
| Final | 6/6/2023 | OK to Issue CofO | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | JACK KARGODORIAN |