4251 N FORMAN AVE 91602

Certificate Information: 4251 N FORMAN AVE 91602

Application / Permit
22010-20000-02076
Plan Check / Job No.
B22VN06282
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
(N) TRELLIS 18'-0"x33'-6"
Permit Issued
Issued on 11/21/2023
Issuing Office
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 MOHAMMAD ESMAILI
Corrections Issued 5/16/2022 MOHAMMAD ESMAILI
Quality Review Completed 5/17/2022 OMID HEDAYAT
Building Plans Picked Up 5/24/2022 APPLICANT
Applicant returned to address corrections 8/16/2023 MOHAMMAD ESMAILI
Plan Check Approved 11/17/2023 MOHAMMAD ESMAILI
Issued 11/21/2023 APPLICANT
CofO in Progress 1/16/2026 JAVIER RAMOS JR
Permit Finaled 1/29/2026 RUBEN SALAS
CofO Issued 1/29/2026 RUBEN SALAS
Permit Finaled 1/29/2026 RUBEN SALAS

Permit Application Clearance Information

Certificate of Compliance Cleared 5/23/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 5/23/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 5/23/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 5/23/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 5/23/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 6/27/2023 LEE GUILBEAUX
Disturb/Remove Protected Trees Cleared 7/19/2023 ADALBERTO VERA
ZI Cleared 8/21/2023 GEORGIA SMITH
Miscellaneous Cleared 11/17/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2023 Partial Approval DAVID MATSON
Footing/Foundation/Slab 12/18/2023 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/22/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 8/22/2025 Approved JAVIER RAMOS JR
Final 8/22/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Final 8/22/2025 Partial Inspection JAVIER RAMOS JR
PLUMBING-Final 8/22/2025 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/22/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/29/2025 Not Ready for Inspection MISAEL ESPARZA
Final 8/29/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 9/10/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/15/2026 Approved JAVIER RAMOS JR
Final 1/15/2026 OK to Issue CofO JAVIER RAMOS JR