4251 N FORMAN AVE 91602

Certificate Information: 4251 N FORMAN AVE 91602

Application / Permit
22010-20000-02075
Plan Check / Job No.
B22VN06282
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD AND ATT. GARAGE ; fire sprinkler nfpa-13d
Permit Issued
Issued on 10/11/2023
Issuing Office
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 MOHAMMAD ESMAILI
Corrections Issued 5/16/2022 MOHAMMAD ESMAILI
Quality Review Completed 5/17/2022 OMID HEDAYAT
Building Plans Picked Up 5/24/2022 APPLICANT
Applicant returned to address corrections 8/16/2023 MOHAMMAD ESMAILI
Plan Check Approved 10/6/2023 MOHAMMAD ESMAILI
Issued 10/11/2023 APPLICANT
CofO in Progress 1/16/2026 JAVIER RAMOS JR
Permit Finaled 1/29/2026 RUBEN SALAS
CofO Issued 1/29/2026 RUBEN SALAS
Permit Finaled 1/29/2026 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/24/2023 MATTHEW CRAIG
Low Impact Development Cleared 5/8/2023 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 5/19/2023 LEE GUILBEAUX
Certificate of Compliance Cleared 5/23/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 5/23/2023 LEE GUILBEAUX
Miscellaneous Cleared 5/23/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 5/23/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 5/23/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 5/23/2023 NELSON RODRIGUEZ
Sewer availability Cleared 5/23/2023 LEE GUILBEAUX
Disturb/Remove Protected Trees Cleared 7/19/2023 ADALBERTO VERA
Address approval Cleared 8/21/2023 LEE GUILBEAUX
ZI Cleared 8/21/2023 GEORGIA SMITH
Miscellaneous Cleared 10/6/2023 LEE GUILBEAUX
Hold Cleared 8/20/2025 SANDRA SOH

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2023 Partial Approval DAVID MATSON
Footing/Foundation/Slab 12/1/2023 Partial Approval DAVID MATSON
PLUMBING-Rough 12/1/2023 Partial Approval DAVID MATSON
Underground Mechanical 12/1/2023 Not Ready for Inspection DAVID MATSON
Deputy Reinf. Concrete 12/4/2023 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 12/8/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 12/18/2023 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 12/27/2023 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 1/12/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 1/16/2024 Approved KIRK SANDERS
Deputy Reinf. Concrete 1/24/2024 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 3/19/2024 Approved CHRISTOPHER ROJAS
Special/Order Compliance 3/19/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 3/21/2024 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 3/21/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Corrections Issued KIRK SANDERS
Deputy Drilled-In Anchors 4/24/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 4/24/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/24/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/25/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 4/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 4/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 5/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 6/4/2024 Partial Approval CHRISTOPHER ROJAS
Pre-Inspection 6/7/2024 Approved VINCENT HANLEY
PLUMBING-Rough 6/28/2024 Approved SALVADOR MARTINEZ
Shower Pan 7/2/2024 Approved CHRISTOPHER ROJAS
Wood Frame 7/2/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 7/3/2024 Approved SALVADOR MARTINEZ
Shower Pan 7/3/2024 Partial Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/1/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 8/1/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 8/1/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 8/1/2024 Approved CHRISTOPHER ROJAS
Insulation 9/11/2024 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/11/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/13/2024 Approved CHRISTOPHER ROJAS
Insulation 10/18/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/4/2024 Partial Approval MICHAEL CORTEZ
Drywall Nailing 11/18/2024 Approved LOUIS ESCOTO
Sewer 4/8/2025 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 4/8/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 7/22/2025 Approved JAVIER RAMOS JR
HVAC-Final 8/1/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 8/1/2025 Corrections Issued JAVIER RAMOS JR
Service/Power Release 8/1/2025 Approved JAVIER RAMOS JR
Final 8/22/2025 Partial Inspection JAVIER RAMOS JR
Green Building Final 8/22/2025 Approved JAVIER RAMOS JR
HVAC-Final 8/22/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 8/22/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/22/2025 Approved JAVIER RAMOS JR
Service/Power Release 9/26/2025 Approved JAVIER RAMOS JR
Special/Order Compliance 11/5/2025 Corrections Issued JUAN VALENZUELA
Final 1/15/2026 OK to Issue CofO JAVIER RAMOS JR