6419 N WILBUR AVE 91335
Certificate Information: 6419 N WILBUR AVE 91335
- Application / Permit
- 22010-20000-02043
- Plan Check / Job No.
- B22VN06191
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan new ADU. NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) 1 of 2.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | MONICA RAMIREZ |
| Corrections Issued | 5/19/2022 | MONICA RAMIREZ |
| Quality Review Completed | 5/24/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/5/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/28/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/21/2022 | MONICA RAMIREZ |
| Plan Check Approved | 12/22/2022 | MONICA RAMIREZ |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 3/18/2024 | JON MCHUGH |
| Permit Finaled | 4/12/2024 | JOHN JANSON |
| CofO Issued | 4/12/2024 | JOHN JANSON |
| Permit Finaled | 4/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | CARLOS AGUILERA |
| ZI | Cleared | 8/2/2022 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 10/26/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 10/27/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/17/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/30/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 4/24/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 4/24/2023 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 4/27/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 4/27/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 5/5/2023 | Approved | JON MCHUGH |
| Green Building Rough | 5/5/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 5/5/2023 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 5/5/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 7/26/2023 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/26/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/26/2023 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 7/26/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/26/2023 | Approved | VINCENT HANLEY |
| Insulation | 8/4/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 8/4/2023 | Partial Approval | JON MCHUGH |
| Drywall Nailing | 8/10/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 8/10/2023 | Approved | JON MCHUGH |
| Shower Pan | 8/10/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | JON MCHUGH |
| Final | 11/2/2023 | No Access for Inspection | JON MCHUGH |
| Green Building Final | 11/2/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 11/2/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 11/2/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 11/2/2023 | No Access for Inspection | JON MCHUGH |
| Final | 1/12/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 1/12/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 1/12/2024 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 1/12/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 1/30/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 1/30/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 1/30/2024 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 1/30/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 2/13/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 2/13/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 2/13/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 2/13/2024 | Approved | JON MCHUGH |
| Service/Power Release | 2/13/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 3/18/2024 | Approved | JON MCHUGH |
| Final | 3/18/2024 | OK to Issue CofO | JON MCHUGH |
| Service/Power Release | 3/18/2024 | Approved | JON MCHUGH |