22548-22550 W MARLIN PL 91307

Certificate Information: 22548-22550 W MARLIN PL 91307

Application / Permit
22010-20000-02035
Plan Check / Job No.
B22VN06166
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert Existing attached Garage to Accessory Dwelling Unit per CA Gov't code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
CofO Issued on 12/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2022 APPLICANT
Assigned to Plan Check Engineer 4/26/2022 HANS SANTIAGO
Corrections Issued 4/27/2022 HANS SANTIAGO
Plan Check Approved 6/16/2022 ANDREW SANTIAGO
Issued 6/16/2022 APPLICANT
CofO in Progress 11/15/2022 TROY SANDERS
Permit Finaled 12/21/2022 JOHN JANSON
CofO Issued 12/21/2022 JOHN JANSON
Permit Finaled 12/21/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/5/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/5/2022 CARLOS AGUILERA
Sewer availability Cleared 5/5/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Xia,, Ji; Lic. No.: NA89014       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/12/2022 Approved TROY SANDERS
PLUMBING-Rough 7/18/2022 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 8/4/2022 Partial Approval TROY SANDERS
ELECTRICAL-Rough 8/4/2022 Approved TROY SANDERS
Green Building Rough 8/4/2022 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 8/4/2022 Partial Approval TROY SANDERS
HVAC-Rough 8/12/2022 Approved TROY SANDERS
Insulation 8/12/2022 Approved TROY SANDERS
PLUMBING-Rough 8/12/2022 Approved TROY SANDERS
Drywall Nailing 8/24/2022 Partial Approval TROY SANDERS
Green Building Rough 8/24/2022 Not Ready for Inspection TROY SANDERS
Shower Pan 9/21/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 11/14/2022 Approved TROY SANDERS
Drywall Nailing 11/14/2022 Approved TROY SANDERS
ELECTRICAL-Final 11/14/2022 Approved TROY SANDERS
Final 11/14/2022 Corrections Issued TROY SANDERS
Green Building Final 11/14/2022 Approved TROY SANDERS
Green Building Rough 11/14/2022 Approved TROY SANDERS
HVAC-Final 11/14/2022 Approved TROY SANDERS
PLUMBING-Final 11/14/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/14/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 11/14/2022 Approved TROY SANDERS
Final 11/15/2022 OK to Issue CofO TROY SANDERS