5109 N BLUEBELL AVE 91607

Certificate Information: 5109 N BLUEBELL AVE 91607

Application / Permit
22010-20000-02023
Plan Check / Job No.
B22VN06129
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 10/26/2022
Issuing Office
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 MICHAEL LOPEZ
Corrections Issued 5/22/2022 MICHAEL LOPEZ
Quality Review Completed 5/26/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/11/2022 MICHAEL LOPEZ
Applicant returned to address corrections 7/27/2022 MICHAEL LOPEZ
Applicant returned to address corrections 8/10/2022 MICHAEL LOPEZ
Applicant returned to address corrections 9/6/2022 MICHAEL LOPEZ
Applicant returned to address corrections 9/20/2022 MICHAEL LOPEZ
Plan Check Approved 10/24/2022 HERNAN ARREOLA
Issued 10/26/2022 APPLICANT
CofO in Progress 2/21/2025 OGANES TARAKHCHYAN
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 5/19/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 5/19/2022 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 5/20/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 5/20/2022 KURT CORRAL
Sewer availability Cleared 5/20/2022 DAGOVERTO GUERRERO
Highway dedication Cleared 5/24/2022 DAGOVERTO GUERRERO
Permit Cleared 5/24/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 6/13/2022 TA ANH
Roof/Waste drainage to street Cleared 6/16/2022 ROMAN GUTIERREZ
Trees in Parkway Cleared 6/22/2022 ADALBERTO VERA
Specific Plan Cleared 7/5/2022 CORREY KITCHENS
Tract Map conditions Cleared 8/16/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 8/17/2022 DANG NGUYEN
Address approval Cleared 9/7/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/12/2023 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 4/12/2023 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/20/2023 Approved JOHN COLEMAN
Deputy Reinf. Concrete 4/24/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Partial Approval KIRK SANDERS
Deputy Wood Construction 5/8/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 5/11/2023 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 5/18/2023 Approved KIRK SANDERS
Rough-Elec/Plmb/HVAC 5/18/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 5/24/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 5/24/2023 Approved KIRK SANDERS
PLUMBING-Rough 5/24/2023 Approved KIRK SANDERS
Wood Frame 5/24/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 6/2/2023 Corrections Issued KIRK SANDERS
Sewer 6/2/2023 Not Ready for Inspection KIRK SANDERS
Wood Frame 6/2/2023 Corrections Issued KIRK SANDERS
Shower Pan 6/5/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Approved KIRK SANDERS
Green Building Rough 6/15/2023 Not Ready for Inspection KIRK SANDERS
Interior/Exterior Lathing 6/15/2023 Partial Approval KIRK SANDERS
Verify Sprinkler Sign Off 6/15/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 6/22/2023 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 6/27/2023 Approved KIRK SANDERS
Green Building Rough 6/27/2023 Approved KIRK SANDERS
Insulation 6/27/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 6/27/2023 Approved KIRK SANDERS
Shower Pan 6/27/2023 Approved KIRK SANDERS
Drywall Nailing 7/3/2023 Approved KIRK SANDERS
Gas Test 7/3/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 3/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 3/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 3/18/2024 Approved JOSE AVILA
HVAC-Final 4/17/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/17/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/19/2024 Approved JOSE AVILA
PLUMBING-Final 4/19/2024 Approved JOSE AVILA
Service/Power Release 5/3/2024 Approved JOSE AVILA
Final 10/22/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 10/22/2024 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 10/22/2024 Approved OGANES TARAKHCHYAN
Final 2/6/2025 Conditional Approval GAREN HAYRAPETYAN
Green Building Final 2/6/2025 Approved GAREN HAYRAPETYAN
Final 2/12/2025 OK to Issue CofO OGANES TARAKHCHYAN