7421 N AMIGO AVE 91335
Certificate Information: 7421 N AMIGO AVE 91335
- Application / Permit
- 22010-20000-02021
- Plan Check / Job No.
- B22VN06125
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- Current Status
- CofO Issued on 12/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2022 | CARLOS MONTES |
| Corrections Issued | 4/26/2022 | CARLOS MONTES |
| Plan Check Approved | 5/8/2022 | CARLOS MONTES |
| Issued | 5/9/2022 | APPLICANT |
| CofO in Progress | 10/19/2022 | JEFFREY BULL |
| CofO Issued | 12/20/2022 | MICHAEL SMITH |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/28/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2022 | MEGAN GODINEZ |
| ZA Case | Cleared | 5/2/2022 | PABLO ESTRADA |
| Hold | Cleared | 5/18/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/19/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/26/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/26/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/26/2022 | Partial Approval | VINCENT HANLEY |
| Pre-Inspection | 5/26/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/23/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| Sewer | 6/23/2022 | Approved | VINCENT HANLEY |
| Underground Mechanical | 6/23/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 8/22/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 8/22/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/22/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 8/22/2022 | Approved | JUSTIN HAWLEY |
| Final | 9/29/2022 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 9/29/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 9/29/2022 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 9/29/2022 | Approved | JEFFREY BULL |
| Final | 10/18/2022 | OK to Issue CofO | JEFFREY BULL |
| Service/Power Release | 10/18/2022 | Approved | JEFFREY BULL |