7421 N AMIGO AVE 91335

Certificate Information: 7421 N AMIGO AVE 91335

Application / Permit
22010-20000-02021
Plan Check / Job No.
B22VN06125
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 5/9/2022
Issuing Office
Current Status
CofO Issued on 12/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2022 APPLICANT
Assigned to Plan Check Engineer 4/25/2022 CARLOS MONTES
Corrections Issued 4/26/2022 CARLOS MONTES
Plan Check Approved 5/8/2022 CARLOS MONTES
Issued 5/9/2022 APPLICANT
CofO in Progress 10/19/2022 JEFFREY BULL
CofO Issued 12/20/2022 MICHAEL SMITH
Permit Finaled 12/20/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/28/2022 MEGAN GODINEZ
Sewer availability Cleared 4/28/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/29/2022 MEGAN GODINEZ
ZA Case Cleared 5/2/2022 PABLO ESTRADA
Hold Cleared 5/18/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/26/2022 Not Ready for Inspection VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/26/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/26/2022 Approved VINCENT HANLEY
PLUMBING-Rough 5/26/2022 Partial Approval VINCENT HANLEY
Pre-Inspection 5/26/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/23/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 6/23/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Approved VINCENT HANLEY
Green Building Rough 6/23/2022 Approved VINCENT HANLEY
PLUMBING-Rough 6/23/2022 Approved VINCENT HANLEY
Sewer 6/23/2022 Approved VINCENT HANLEY
Underground Mechanical 6/23/2022 Approved VINCENT HANLEY
Drywall Nailing 8/22/2022 Approved JUSTIN HAWLEY
Insulation 8/22/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 8/22/2022 Approved JUSTIN HAWLEY
Shower Pan 8/22/2022 Approved JUSTIN HAWLEY
Final 9/29/2022 Corrections Issued JEFFREY BULL
Green Building Final 9/29/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Approved JEFFREY BULL
Smoke Detectors 9/29/2022 Approved JEFFREY BULL
Final 10/18/2022 OK to Issue CofO JEFFREY BULL
Service/Power Release 10/18/2022 Approved JEFFREY BULL