Footing/Foundation/Slab
|
9/29/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/10/2023
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wall Anchors
|
10/10/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/12/2023
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
10/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/17/2023
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
10/18/2023
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Structural Steel Frame
|
10/19/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Wall Anchors
|
10/23/2023
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
11/1/2023
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
11/16/2023
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
11/21/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
11/28/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
11/28/2023
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/4/2023
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
12/4/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/5/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/13/2023
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
12/13/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/14/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/27/2023
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/3/2024
|
Approved
|
DANNY RODRIGUEZ
|
|
Insulation
|
1/3/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
1/3/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
1/3/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/5/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
1/8/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
1/9/2024
|
Approved
|
KENNETH ROBERTS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/11/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Wood Construction
|
1/12/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
1/16/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/16/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
1/22/2024
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Drywall Nailing
|
1/25/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
1/30/2024
|
Approved
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
2/15/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
5/30/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
6/5/2024
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Wood Frame
|
6/5/2024
|
Partial Approval
|
DEANDRE HOFFMAN
|
|
Interior/Exterior Lathing
|
6/10/2024
|
Partial Approval
|
ROBERT DAVIS
|
|
Interior/Exterior Lathing
|
6/18/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
6/24/2024
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
6/26/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
6/28/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
7/1/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Special/Order Compliance
|
8/13/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/19/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/20/2024
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
8/20/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/21/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/22/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
8/22/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
T-Bar Ceiling
|
10/4/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
2/10/2025
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Special/Order Compliance
|
6/10/2025
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
7/30/2025
|
No Access for Inspection
|
ROBERT DAVIS
|
|
Final
|
7/30/2025
|
No Access for Inspection
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
7/30/2025
|
No Access for Inspection
|
ROBERT DAVIS
|
|
Green Building Final
|
7/30/2025
|
No Access for Inspection
|
ROBERT DAVIS
|
|
SGSOV-Seismic Gas S/O Valve
|
7/30/2025
|
SGSOV Not Ready
|
ROBERT DAVIS
|
|
Smoke Detectors
|
7/30/2025
|
No Access for Inspection
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
7/30/2025
|
No Access for Inspection
|
ROBERT DAVIS
|
|
Wood Frame
|
7/30/2025
|
No Access for Inspection
|
ROBERT DAVIS
|
|
Drywall Nailing
|
8/4/2025
|
Approved
|
ROBERT DAVIS
|
|
Final
|
8/4/2025
|
Partial Inspection
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
8/4/2025
|
Approved
|
ROBERT DAVIS
|
|
Green Building Final
|
8/4/2025
|
Approved
|
ROBERT DAVIS
|
|
SGSOV-Seismic Gas S/O Valve
|
8/4/2025
|
SGSOV Not Ready
|
ROBERT DAVIS
|
|
Smoke Detectors
|
8/4/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
8/4/2025
|
Approved
|
ROBERT DAVIS
|
|
Wood Frame
|
8/4/2025
|
Approved
|
ROBERT DAVIS
|
|
Final
|
8/11/2025
|
Partial Inspection
|
ROBERT DAVIS
|
|
SGSOV-Seismic Gas S/O Valve
|
8/11/2025
|
SGSOV Approved
|
ROBERT DAVIS
|
|
Smoke Detectors
|
8/11/2025
|
Approved
|
ROBERT DAVIS
|
|
Final
|
8/21/2025
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Final
|
8/27/2025
|
Partial Approval
|
ROBERT DAVIS
|