5413 W PACKARD ST 90019

Certificate Information: 5413 W PACKARD ST 90019

Application / Permit
22010-20000-02009
Plan Check / Job No.
B22VN06068
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
15'x30', 4'x11.5' NEW 496 SQ. FT. DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ****Code Enforcement Bureau has issued an order. This parcel is eligible for issuance of a 30 day time limit permit (including Building, Electrical, HVAC and Plumbing) with a work description as follows. "COMPLY WITH DEPARTMENT ORDER effective date 12/24/2010. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector JEFFREY CHRISTIAN at (213)252-3957 of GENERAL ENFORCEMENT SOUTH. CEIS Case Number is 397368. (Created: IMSV7 / 12-13-10)***
Permit Issued
Issued on 8/26/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2022 APPLICANT
Assigned to Plan Check Engineer 4/27/2022 JESSE ARELLANO
Corrections Issued 4/28/2022 JESSE ARELLANO
Building Plans Picked Up 5/3/2022 APPLICANT
Applicant returned to address corrections 7/25/2022 ROSENDO MEDINA
Applicant returned to address corrections 8/17/2022 ALEC MOUSAKHANIAN
Plan Check Approved 8/26/2022 KHUONG TRUONG
Issued 8/26/2022 APPLICANT
CofO in Progress 8/11/2023 GLEN RAND
Permit Finaled 9/5/2023 BRUCE TODD
CofO Issued 9/5/2023 BRUCE TODD
Permit Finaled 9/5/2023 BRUCE TODD

Permit Application Clearance Information

Sewer availability Cleared 5/11/2022 STEVE MELGAR
Address approval Cleared 5/18/2022 STEVE MELGAR
Low Impact Development Cleared 6/16/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/22/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/25/2022 STEVE MELGAR
Construction near power lines Cleared 7/28/2022 RIDWAN HARDY
Green Code Cleared 8/17/2022 JESSE ARELLANO

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B 20520 OXNARD ST      WOODLAND, CA 91367
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/24/2022 Corrections Issued GLEN RAND
METHANE-Barrier 10/24/2022 Approved GLEN RAND
METHANE-Subgrade 10/24/2022 Approved GLEN RAND
Footing/Foundation/Slab 10/25/2022 Approved GLEN RAND
BUILDING-Rough-Frame 11/1/2022 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 11/1/2022 Not Ready for Inspection WILLIAM MICHALAK
Insulation 11/1/2022 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 11/1/2022 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Rough 11/1/2022 Not Ready for Inspection WILLIAM MICHALAK
Verify Sprinkler Sign Off 11/1/2022 Not Ready for Inspection WILLIAM MICHALAK
Insulation 11/2/2022 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Rough 11/2/2022 Approved WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Approved WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Inspection GLEN RAND
Deputy Wood Construction 12/7/2022 Approved GLEN RAND
BUILDING-Rough-Frame 12/8/2022 Partial Approval GLEN RAND
Rough-Elec/Plmb/HVAC 1/31/2023 Corrections Issued GLEN RAND
Rough-Elec/Plmb/HVAC 2/1/2023 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 2/14/2023 Approved GLEN RAND
Green Building Rough 2/14/2023 Approved GLEN RAND
METHANE-Rough 2/14/2023 Approved GLEN RAND
Rough-Elec/Plmb/HVAC 2/14/2023 Approved GLEN RAND
Underground Mechanical 2/14/2023 Not Ready for Inspection GLEN RAND
Verify Sprinkler Sign Off 2/14/2023 Partial Inspection GLEN RAND
Insulation 2/22/2023 Approved WILLIAM MICHALAK
Drywall Nailing 2/27/2023 Approved GLEN RAND
Interior/Exterior Lathing 2/28/2023 Approved GLEN RAND
Underground Mechanical 4/3/2023 Approved WILLIAM MICHALAK
ELECTRICAL-Final 4/24/2023 Corrections Issued GLEN RAND
Final 6/12/2023 Corrections Issued GLEN RAND
Green Building Final 6/12/2023 Not Ready for Inspection GLEN RAND
SGSOV-Seismic Gas S/O Valve 6/12/2023 SGSOV Approved GLEN RAND
Service/Power Release 6/12/2023 Not Ready for Inspection GLEN RAND
Smoke Detectors 6/12/2023 Approved GLEN RAND
Final 6/16/2023 Not Ready for Inspection GLEN RAND
Green Building Final 6/16/2023 Not Ready for Inspection GLEN RAND
Final 8/11/2023 OK to Issue CofO GLEN RAND
Green Building Final 8/11/2023 Approved GLEN RAND