5413 W PACKARD ST 90019
Certificate Information: 5413 W PACKARD ST 90019
- Application / Permit
- 22010-20000-02009
- Plan Check / Job No.
- B22VN06068
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'x30', 4'x11.5' NEW 496 SQ. FT. DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ****Code Enforcement Bureau has issued an order. This parcel is eligible for issuance of a 30 day time limit permit (including Building, Electrical, HVAC and Plumbing) with a work description as follows. "COMPLY WITH DEPARTMENT ORDER effective date 12/24/2010. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector JEFFREY CHRISTIAN at (213)252-3957 of GENERAL ENFORCEMENT SOUTH. CEIS Case Number is 397368. (Created: IMSV7 / 12-13-10)***
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2022 | JESSE ARELLANO |
| Corrections Issued | 4/28/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| Applicant returned to address corrections | 7/25/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 8/17/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/26/2022 | KHUONG TRUONG |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 8/11/2023 | GLEN RAND |
| Permit Finaled | 9/5/2023 | BRUCE TODD |
| CofO Issued | 9/5/2023 | BRUCE TODD |
| Permit Finaled | 9/5/2023 | BRUCE TODD |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/11/2022 | STEVE MELGAR |
| Address approval | Cleared | 5/18/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 6/16/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/22/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 7/28/2022 | RIDWAN HARDY |
| Green Code | Cleared | 8/17/2022 | JESSE ARELLANO |
Contact Information
| Contractor | F S Design & Construction Inc; Lic. No.: 727272-B | 20520 OXNARD ST WOODLAND, CA 91367 |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/24/2022 | Corrections Issued | GLEN RAND |
| METHANE-Barrier | 10/24/2022 | Approved | GLEN RAND |
| METHANE-Subgrade | 10/24/2022 | Approved | GLEN RAND |
| Footing/Foundation/Slab | 10/25/2022 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 11/1/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Rough | 11/1/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Insulation | 11/1/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Rough | 11/1/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| PLUMBING-Rough | 11/1/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Verify Sprinkler Sign Off | 11/1/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Insulation | 11/2/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| PLUMBING-Rough | 11/2/2022 | Approved | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Approved | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Inspection | GLEN RAND |
| Deputy Wood Construction | 12/7/2022 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 12/8/2022 | Partial Approval | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 1/31/2023 | Corrections Issued | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 2/1/2023 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 2/14/2023 | Approved | GLEN RAND |
| Green Building Rough | 2/14/2023 | Approved | GLEN RAND |
| METHANE-Rough | 2/14/2023 | Approved | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 2/14/2023 | Approved | GLEN RAND |
| Underground Mechanical | 2/14/2023 | Not Ready for Inspection | GLEN RAND |
| Verify Sprinkler Sign Off | 2/14/2023 | Partial Inspection | GLEN RAND |
| Insulation | 2/22/2023 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 2/27/2023 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 2/28/2023 | Approved | GLEN RAND |
| Underground Mechanical | 4/3/2023 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Final | 4/24/2023 | Corrections Issued | GLEN RAND |
| Final | 6/12/2023 | Corrections Issued | GLEN RAND |
| Green Building Final | 6/12/2023 | Not Ready for Inspection | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | GLEN RAND |
| Service/Power Release | 6/12/2023 | Not Ready for Inspection | GLEN RAND |
| Smoke Detectors | 6/12/2023 | Approved | GLEN RAND |
| Final | 6/16/2023 | Not Ready for Inspection | GLEN RAND |
| Green Building Final | 6/16/2023 | Not Ready for Inspection | GLEN RAND |
| Final | 8/11/2023 | OK to Issue CofO | GLEN RAND |
| Green Building Final | 8/11/2023 | Approved | GLEN RAND |