Work Description
PROPOSE ONE STORY ACCESSORY DWELLING UNIT (PER GCS 65852.2(e)(1)(B) and GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)) _BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 12/15/2022
Issuing Office
Valley
Current Status
CofO in Progress on 4/12/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/20/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 DAWN MC NULTY
Corrections Issued 5/9/2022 DAWN MC NULTY
Quality Review Completed 5/12/2022 STEVEN KIM
Building Plans Picked Up 5/13/2022 APPLICANT
Applicant returned to address corrections 7/26/2022 DAWN MC NULTY
Applicant returned to address corrections 11/9/2022 DAWN MC NULTY
Applicant returned to address corrections 12/5/2022 DAWN MC NULTY
Plan Check Approved 12/15/2022 DAWN MC NULTY
Issued 12/15/2022 APPLICANT
CofO in Progress 4/12/2024 VINCENT HANLEY

Permit Application Clearance Information

Address approval Cleared 5/17/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/17/2022 CARLOS AGUILERA
Sewer availability Cleared 5/17/2022 CARLOS AGUILERA
Low Impact Development Cleared 6/15/2022 CHRIS VONG
Hydrant and Access approval Cleared 6/25/2022 JOHN CONNEALLY
CPC Cleared 6/27/2022 DANG NGUYEN
Roof/Waste drainage to street Cleared 7/2/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 7/26/2022 DAWN MC NULTY
Grading Pre-Inspection Cleared 7/26/2022 DAWN MC NULTY

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/27/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 1/27/2023 Approved VINCENT HANLEY
PLUMBING-Rough 1/27/2023 Partial Approval VINCENT HANLEY
Sewer 1/27/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/2/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Approved VINCENT HANLEY
PLUMBING-Rough 6/8/2023 Approved VINCENT HANLEY
Green Building Rough 7/20/2023 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 7/25/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 7/25/2023 Approved VINCENT HANLEY
Green Building Rough 7/25/2023 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 7/25/2023 Approved VINCENT HANLEY
Shower Pan 7/25/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/25/2023 Approved VINCENT HANLEY
Wood Frame 7/25/2023 Approved VINCENT HANLEY
Drywall Nailing 8/7/2023 Approved VINCENT HANLEY
Green Building Rough 8/7/2023 Approved VINCENT HANLEY
Insulation 8/7/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/7/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/19/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 3/19/2024 Approved VINCENT HANLEY
Final 3/19/2024 Corrections Issued VINCENT HANLEY
Green Building Final 3/19/2024 Approved VINCENT HANLEY
HVAC-Final 3/19/2024 Corrections Issued VINCENT HANLEY
PLUMBING-Final 3/19/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 3/19/2024 Approved VINCENT HANLEY
Smoke Detectors 3/19/2024 Approved VINCENT HANLEY
Final 3/27/2024 Corrections Issued VINCENT HANLEY
HVAC-Final 3/27/2024 Approved VINCENT HANLEY
Final 4/8/2024 Corrections Issued VINCENT HANLEY
Final 4/12/2024 OK to Issue CofO VINCENT HANLEY