6550 N MORSE AVE 91606

Certificate Information: 6550 N MORSE AVE 91606

Application / Permit
22010-20000-01969
Plan Check / Job No.
B22VN05879
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED ADU (19'-4"x40'-0"), 1171 SQFT PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 1/8/2024
Issuing Office
Current Status
CofO Issued on 2/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 PETER MOSESIAN
Corrections Issued 5/13/2022 PETER MOSESIAN
Quality Review Completed 5/27/2022 OMID HEDAYAT
Building Plans Picked Up 6/8/2022 APPLICANT
Plan Check Approved 1/8/2024 PETER MOSESIAN
Issued 1/8/2024 APPLICANT
CofO in Progress 2/10/2025 OGANES TARAKHCHYAN
Permit Finaled 2/19/2025 RUBEN SALAS
CofO Issued 2/19/2025 RUBEN SALAS
Permit Finaled 2/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/4/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 8/5/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 8/5/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 9/2/2022 MATTHEW CRAIG
Construction near power lines Cleared 1/27/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 12/26/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 12/28/2023 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/14/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 2/14/2024 Partial Approval JOSE AVILA
Footing/Foundation/Slab 2/15/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 2/28/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/1/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Corrections Issued JOSE AVILA
Deputy Wood Construction 6/11/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 6/12/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 6/12/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/5/2024 Approved JOSE AVILA
HVAC-Rough 7/5/2024 Partial Approval JOSE AVILA
Interior/Exterior Lathing 7/5/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 7/5/2024 Approved JOSE AVILA
Insulation 7/10/2024 Corrections Issued SALVADOR MARTINEZ
Insulation 7/17/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/17/2024 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 7/17/2024 Not Ready for Inspection JACK KARGODORIAN
Drywall Nailing 8/5/2024 Approved MISAEL ESPARZA
Green Building Rough 8/5/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/5/2024 Approved MISAEL ESPARZA
Shower Pan 8/5/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/19/2024 Approved GAREN HAYRAPETYAN
Final 12/19/2024 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 12/19/2024 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Not Ready GAREN HAYRAPETYAN
Service/Power Release 12/19/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 12/19/2024 Corrections Issued GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 12/19/2024 Approved GAREN HAYRAPETYAN
Final 1/22/2025 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 1/22/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 1/22/2025 Approved GAREN HAYRAPETYAN
Final 1/27/2025 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 1/27/2025 Approved OGANES TARAKHCHYAN
Service/Power Release 2/11/2025 Approved OGANES TARAKHCHYAN