19033 W NAPA ST 91324

Certificate Information: 19033 W NAPA ST 91324

Application / Permit
22010-20000-01942
Plan Check / Job No.
B22VN05821
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan new detached 600 sq. ft. one story A.D.U. PER STATE LAW
Permit Issued
Issued on 7/26/2022
Issuing Office
Current Status
CofO Issued on 4/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2022 APPLICANT
Assigned to Plan Check Engineer 4/22/2022 RACHEL BEYENE
Corrections Issued 4/22/2022 CARLOS MONTES
Applicant returned to address corrections 7/21/2022 PRANITA SHAH
Plan Check Approved 7/24/2022 RAHEL BEYENE
Issued 7/26/2022 APPLICANT
CofO in Progress 3/30/2023 DAVID SCANTLIN
Permit Finaled 4/20/2023 JOHN JANSON
CofO Issued 4/20/2023 JOHN JANSON
Permit Finaled 4/20/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/11/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/12/2022 MEGAN GODINEZ
Sewer availability Cleared 5/17/2022 MEGAN GODINEZ
Low Impact Development Cleared 6/24/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/24/2022 JOHN LIN
Construction near power lines Cleared 7/13/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/20/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 10/21/2022 Partial Inspection JOHN KIDWELL
Special/Order Compliance 10/21/2022 Partial Approval MORRIS JACKSON
Special/Order Compliance 10/21/2022 Partial Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 10/26/2022 Corrections Issued JOHN KIDWELL
Pre-Inspection 10/26/2022 Approved JUSTIN HAWLEY
Special/Order Compliance 10/26/2022 Partial Inspection MORRIS JACKSON
ELECTRICAL-Rough 11/22/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Approved JOHN KIDWELL
HVAC-Rough 11/22/2022 Approved JOHN KIDWELL
PLUMBING-Rough 11/22/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 12/1/2022 Approved JOHN KIDWELL
Insulation 12/1/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/1/2022 Partial Approval JOHN KIDWELL
Pre-Inspection 12/1/2022 Partial Inspection JUSTIN HAWLEY
Special/Order Compliance 12/1/2022 Partial Inspection MORRIS JACKSON
Verify Sprinkler Sign Off 12/1/2022 Approved JOHN KIDWELL
Drywall Nailing 12/6/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/6/2022 Partial Approval JOHN KIDWELL
Gas Test 1/19/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Final 2/9/2023 Not Ready for Inspection MORRIS JACKSON
Final 2/9/2023 Not Ready for Inspection MORRIS JACKSON
Footing/Foundation/Slab 2/9/2023 Corrections Issued MORRIS JACKSON
HVAC-Final 2/9/2023 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Final 2/9/2023 Not Ready for Inspection MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Not Ready MORRIS JACKSON
Service/Power Release 2/9/2023 Not Ready for Inspection MORRIS JACKSON
Smoke Detectors 2/9/2023 Not Ready for Inspection MORRIS JACKSON
Special/Order Compliance 2/9/2023 Approved DAVID SCANTLIN
ELECTRICAL-Final 2/24/2023 Approved DAVID SCANTLIN
Final 2/24/2023 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 2/24/2023 Partial Approval DAVID SCANTLIN
HVAC-Final 2/24/2023 Approved DAVID SCANTLIN
PLUMBING-Final 2/24/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Approved DAVID SCANTLIN
Service/Power Release 2/24/2023 Approved DAVID SCANTLIN
Smoke Detectors 2/24/2023 Approved DAVID SCANTLIN
Final 3/30/2023 OK to Issue CofO DAVID SCANTLIN
Footing/Foundation/Slab 3/30/2023 Approved DAVID SCANTLIN