4320 N TEESDALE AVE 91604
Certificate Information: 4320 N TEESDALE AVE 91604
- Application / Permit
- 22010-20000-01935
- Plan Check / Job No.
- B22VN05782
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW ONE STORY DETACHED (13'-0"x19'-6"), 199 SQFT RECREATION ROOM
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | PETER MOSESIAN |
| Corrections Issued | 5/1/2022 | PETER MOSESIAN |
| Quality Review Completed | 5/6/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/12/2022 | APPLICANT |
| Plan Check Approved | 10/27/2022 | PETER MOSESIAN |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 4/29/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 6/24/2024 | RUBEN SALAS |
| CofO Issued | 6/24/2024 | RUBEN SALAS |
| Permit Finaled | 6/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2022 | LEE GUILBEAUX |
| ZI | Cleared | 6/13/2022 | MIGUEL GAMBOA |
| Construction near power lines | Cleared | 6/22/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 7/22/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 9/21/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/21/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/6/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 7/10/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 7/10/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/17/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 7/17/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/24/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/24/2023 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 8/14/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 8/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 8/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Insulation | 8/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/18/2023 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 8/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/23/2023 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/23/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 8/23/2023 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/23/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/30/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 9/5/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 2/13/2024 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 2/15/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 2/15/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 2/15/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/28/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 2/28/2024 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/28/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 2/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/4/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Service/Power Release | 4/4/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 4/25/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 4/25/2024 | No Access for Inspection | JOHN COLEMAN |
| Final | 4/29/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 4/29/2024 | Approved | CHRISTOPHE COCHRAN |